Don't Go For PMP EXAM 2024 Without Understanding Qualitative Risk Analysis Factors!

Sdílet
Vložit
  • čas přidán 26. 10. 2023
  • Want to understand the important factors that will help to do qualitative risk Analysis in a way that you will never forget? In this latest video, our expert trainer, Gautham Sudakar, dives deep into those factors. If you're gearing up for the current PMP exam or just looking to enhance your project management skills, this is a must-watch!
    In this informative session, Gautham shares essential knowledge about four factors going beyond the standard probability and impact assessments. Learn how to prioritize risks effectively using four key factors:
    1. Proximity: Understand the critical factor of time - the window within which risk can impact your project objectives, be it time, cost, or quality.
    2. Urgency: Discover the importance of timing when it comes to implementing risk response plans. Timing is everything!
    3. Dormancy: Explore the period that elapses after a risk has occurred and its impact is felt. Dormancy is a crucial element of risk management that often goes overlooked.
    4. Connectivity: Get insights into the world of risk relationships. Identify high and low connectivity risks, and learn how they can affect your project in different ways.
    But theory alone can be overwhelming. That's why Gautham presents a practical example that brings these concepts to life. Imagine you're a project manager overseeing a construction project. You're planning the foundation work, and your goal is to construct the living room shortly after. What happens if you identify two risks?
    1️⃣ Risk 1: Starting the foundation work on day 3, with concerns about resource availability.
    2️⃣ Risk 2: Initiating the living room construction.
    How do these risks align with the four factors discussed in this video? Gautham breaks it down for you, making it easy to understand and apply to real-world projects.
    Don't miss out on this insightful video that empowers you with the knowledge and skills to excel in qualitative risk management. Whether you're a seasoned project manager or a PMP exam aspirant, this content is a game-changer.
    Hit that 'Subscribe' button, give us a 'Thumbs Up,' and share this video with your fellow project management enthusiasts. Stay tuned for more valuable content from Eduhubspot.
    🔗 Connect with Us
    For any queries, reach out to Gautham at Gautham.sudakar@eduhubspot.com
    Connect with me on LinkedIn directly: / gautham-sudakar-pmp%c2...
    Do check out our PMI Approved PMP Program at:
    www.eduhubspot.com/packages/pmp
    Also, you can email our support team for more questions at services@eduhubspot.com
    Connect with us on WhatsApp: wa.me/message/XVI7DMTEACX7L1
    The last and final step is to move to our website which is very beneficial for the PMP exam prep. www.eduhubspot.com/
    Join our Facebook group: goo.gl/Qhdtn7
    Subscribe to our CZcams Channel: goo.gl/2ZjpEq
    Visit our website for more details: www.eduhubspot.com #PMP #eduhubspot
    Most Awaited video of 2024 is live now. It explains 15 Most Important PMP questions just like real PMP Exam.
    Check out the link: • PMP Certification - Mo...

Komentáře • 112

  • @mathavan6428
    @mathavan6428 Před měsícem +1

    Thank for very good explanation Gautham.
    Scenario 1: Answer: Dormancy - Reason: Here the risk realised. now started to identify the impact. So it will be dormancy.
    Scenario 2: Answer : Connectivity- Reason: The identified risk is connected to so many other activities.
    Scenario 3: Answer: Proximity- Reason:Here we are calculating the risk impact start.
    Scenario 4: Answer: Urgency- Reason- Here identified the risk. and risk response plan also identified.and The time for risk response plan also calculated.

  • @mahmoudsabra9695
    @mahmoudsabra9695 Před 2 měsíci

    Very good example and it seems I understand it from first time
    1- Dormancy
    2- Connectivity
    3- Approximity
    4- Urgency

  • @MG7_GAMER
    @MG7_GAMER Před 8 měsíci +1

    Excellent thanks Gautham. Nidhi suggested that I should watch your videos and these are excellent and Thank you - Aniket

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      Thanks for loving the video.
      Gautham

  • @mananjain1505
    @mananjain1505 Před 8 měsíci +2

    Dormancy - as risk impact can analyze only after risk got realized so, dormancy.
    Connectivity - as risk is connected to lot of other module too.
    Proximity- as we have 30days to to plan response for risk so, proximity
    Urgency - we have 20 days and response plan should be ready to handle the risk so, urgency

  • @remosumo12
    @remosumo12 Před 5 měsíci

    I appreciate your feedback, Gautam. Your clear explanation of qualitative risk analysis concepts truly helped me grasp the subject more easily. Below are my responses to the questions you posed:
    1. The risk has been identified and acknowledged, but we need some time to fully understand its impact - we call this dormancy.
    2. This risk is closely linked to several other modules, indicating its connectivity.
    3. It's expected that this risk will start affecting the project within the next 30 days - we refer to this as proximity.
    4. We've identified this risk and have a plan in place to respond promptly - it's a matter of urgency.
    Thank you once again for your guidance on this topic!

  • @rekhamalavathu
    @rekhamalavathu Před 29 dny

    Hi Gautham, I went through this video before attending my PMP examination over the weekend. I was so confident in answering this question in my actual exam. You made it so clear for me in this video that I will never forget this concept forever. Thanks so much for the practical examples. Loved all your videos. Kuddos to you and your team!

    • @EduHubSpot
      @EduHubSpot  Před 28 dny

      I am so glad that you loved the video.
      Gautham

  • @kiranpilaka9996
    @kiranpilaka9996 Před 5 měsíci

    Thank you Gautham, The explanation is elaborative and clearly clarifies the confusion around understanding the concept. The answers are as below
    Scenario 1: Dormancy because the issue has occurred and the team need more time to identify its impact.
    Scenario 2: Connectivity: Its connected to other modules.
    Scenario 3: Proximity: 30 days within which the risk can be impacted. i.e. time within which risk can impact.
    Scenario 4: Urgency: The risk response plan has already been identified with an elapsed time of 20 days.

  • @elgyalex6811
    @elgyalex6811 Před 8 měsíci +1

    1. Dormancy,
    2.Connectivity
    3.Proximity
    4.Urgency

  • @sansthitachannel324
    @sansthitachannel324 Před 6 měsíci

    Scenario 1 - Dormancy because risk is realized and some time is required to assess its impact
    Scenario 2 - Connectivity because this is connected to other risks of the project
    Scenario 3 - Proximity because I know that the risk will start impacting after a specific period.
    Scenario 4 - Urgency because the risk response plan has been identified.
    Beautifully explained

  • @PravinKalmegh
    @PravinKalmegh Před měsícem

    Proximity : time identified within which risk can impact the project/activity
    Urgency : time within which risk plan must be implemented to avoid the risk
    Very well explained Gautam qualitative analysis concept...

    • @EduHubSpot
      @EduHubSpot  Před měsícem

      Scenario 1 - Dormancy - In this scenario, You must wait for three more days to detect the impact of the risk.
      Scenario 2 - Connectivity - In this scenario, the risk is connected to other modules
      Scenario 3 - Proximity - In this scenario, the risk will start to impact the project objectives within 30 days.
      Scenario 4 - Urgency - In this scenario, the risk response plan has to be completed within 30 days. Here they are talking about the time to complete a risk response plan.
      Thanks for loving the video.
      Gautham

  • @maheshkejriwal9820
    @maheshkejriwal9820 Před 10 dny

    Hi Gautham, thanks for the beautiful explanation. I got the similar question in my PMP exam and I got it quickly.

  • @SubhankarDey-mr9um
    @SubhankarDey-mr9um Před 2 měsíci

    Thanks Gautam. Very well explained.
    1. Dormancy - Risk occured. Need 3 more days to understand the impact.
    2. Connectivity - The risk would impact the other modules of sotware and delay entire project.
    3. Proximity - Impact is identified for 30 days for the software project.
    4. Urgency - Risk identified. Need to mitigate within 20 days to ensure software project is moving as per plan.

    • @EduHubSpot
      @EduHubSpot  Před 2 měsíci

      Very Impressive !!
      Gautham

    • @umeshnamdeo1253
      @umeshnamdeo1253 Před 3 dny

      Thanks Gautam ..very well explained
      1. Dormancy - because we have to wait 3 days to analysis the impact
      2.connectivity - Risk connected with other module of software ,impacting sequential activity also.
      Proximity - impact identified after 30 days
      Urgency - need to mitigate the risk within 20 days to endure software project move as per plan .

  • @Havugi
    @Havugi Před 5 měsíci

    Thanks Gautham for the wonderful video: The Senario 1: The correct answer is Dormancy because the issue has occured and the team need more time to identify its impact which is elapsing time of 3 days. Scenerio 2: It is CONNECTIVITZ because the risk has more conncetion with other module which mean that if occur it will have effect on the remaining or other modules. Scenario 3: it is PROXIMITY as it has 30 days within which the risk can have impact and Scenario 4: URGENCY because the it has the time when the risk response should get implemented of 20 days to be completed.

  • @joyceneba6455
    @joyceneba6455 Před měsícem

    Hello Gautham. I got this particular scenario in my PMP exams and without having watched this video, I would have been entirely lost. I aced my PMP Above Target in all 3 domains in my first try. Your videos were a great help. Thank you.

    • @EduHubSpot
      @EduHubSpot  Před měsícem

      Many Many Congratulations !! I am very happy that my video has helped you in your PMP journey.
      Gautham

  • @phanichaitanya
    @phanichaitanya Před 5 měsíci

    Very well explained

  • @logeshb1101
    @logeshb1101 Před 4 měsíci

    Scenario 1..Dormancy
    Since risk realised
    Scenario 2..Connectivity , since it is connected to many actions
    Scenario 3...Proximity... Since we have 30 days ago within that time we need to plan and arrange
    Scenario 4: Urgency..response plan is planned...
    Great explanation gautham, keep going.. More power to you....

  • @rtchhabria
    @rtchhabria Před 4 měsíci

    why all practical examples are based on construction ??

  • @ajithpaulisaac5074
    @ajithpaulisaac5074 Před 5 měsíci

    Scenario 1 Dormancy. The time elapsed from risk being identified and getting information when we can assess the impact of the risk.

  • @senthivelgopal567
    @senthivelgopal567 Před 5 měsíci

    Urgency : Scenario 4 , the time frame given for implentation of risk response plan after confirming the risk., Proximity - Scenario 3: it is a time delay or duration will actually impact on your activity if the risk not mitigate.here the risk will start impact within 30 days.Dormancy- Scenario 1: the time require further to identify the impact after risk confirmed is three more days so scenario 1 is Dormancy. and finally straight answer to connectivity is scenario 2, because the key word is risk connected to lot of other module.

  • @mailtoaravindan
    @mailtoaravindan Před 5 měsíci

    Thank you Gautham for clear explanation with real time example👍I've given my answers with the explanation below...
    Scenario 1 - The tech. risk is realized and to identify the impact of the risk, we need 3 more days. This is an example of Dormancy. Dormancy is the period of time that may elapse after the risk has occured before its impact is discovered.
    Scenario 2 - Tech. risk is connected to lot of other modules of the software. This is an example of Connectivity. Connectivity is when a risk is connected to many other individual project risks.
    Scenario 3 - Tech. risk will start impacting the project within 30 days. This is an example of Proximity. Proximity is the time within which a risk can make an impact on the project deliverables
    Scenario 4 - Risk Response plan is identified and it has to be completed within 20 days. This is an example of Urgency. Urgency is the time within which a risk response plan should get implemented.

    • @EduHubSpot
      @EduHubSpot  Před 5 měsíci

      Keep up the good work !!
      Gautham

  • @trafirocorera4605
    @trafirocorera4605 Před 5 měsíci

    Scenario 1 is Dormancy as the risk has occurred and it will take time for the team to identify the impact.
    Scenario 2 is Connectivity as the risk is related to other project risks.
    Scenario 3 is proximity as the risk will have positive or negative impact on the project within certain number of days/period.
    Scenario 4 is Urgency as the risk response plan has to be implemented within certain number of days/period.

    • @EduHubSpot
      @EduHubSpot  Před 5 měsíci

      Keep up the good work !!
      Gautham

  • @saravanant9700
    @saravanant9700 Před 8 měsíci

    S-1 Dormancy, S-2 Connectivity, S-3 Proximity, S-4 Urgency

  • @cecilenobi6204
    @cecilenobi6204 Před 8 měsíci

    1-dormancy; 2-connectivity; 3-proximity; 4-urgency

  • @arindambose2636
    @arindambose2636 Před 5 měsíci

    1 Dormancy
    2. Connectivity
    3. Proximity
    4. Urgency

  • @sammistry6759
    @sammistry6759 Před 8 měsíci

    1.Dormancy
    2.Connectivity
    3.Proximity
    4.Urgency

  • @user-hq9hh5si4f
    @user-hq9hh5si4f Před 8 měsíci +2

    Scenario 1 - Dormancy because the impact of risk can be identified after 3 days
    Scenario 2- Connectivity because the risk is connected to other modules
    Scenario 3 - Urgency because the impact time is 30 days ( time related)
    Scenario 4 - Proximity because The impact time is based on the response.

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      Very impressive!! Gautham

    • @emilynsubuga55
      @emilynsubuga55 Před 8 měsíci

      @@EduHubSpot Aren't scenario's 3 and 4 interchanged? I believe urgency reflects time within a risk response plan is to be implemented as stated in Scenario 4 and not 3. Scenario 3 - Shares time of risk impact i.e proximity, Kindly clarify.

  • @AisharyaSG
    @AisharyaSG Před 5 měsíci

    Scenario-1: Dormancy - Impact will be known after certain numbers of days.
    Scenario-2: Connectivity - Risk is connected to other modules too.
    Scenario-3: Proximity - The time within which the risk can impact is mentioned.
    Scenario-4: Urgency - The risk response plan needs to be implemented within 20 days.
    -Aisharya SenGupta.

  • @MayurPatil-fj2fs
    @MayurPatil-fj2fs Před 4 měsíci

    1) Dormancy: After risk got occured it's a waiting period for analysing the further impact..
    2) Connectivity: This is a critical risk (father of risks) on which lot of further risks (children) are dependent.. if this gets delayed then all the dependencies activities will get delayed..
    3) Proximity: How much time do we have till risk occurs..
    4) Urgency: Urgency is the duration say by this this date risk response plan has to be implemented.

  • @kapoorvishal4446
    @kapoorvishal4446 Před 8 měsíci

    Scenario 1 dormancy as the risk already realized.
    Scenario 2 connectivity as this risk has connection to other risks as well
    Scenario 3: proximity as here risk is yet to realize and number of days pending for this to make impact on project is 30 days
    Scenario 4: urgency as risk response plan needs to be implemented by 20 days.

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      That is exactly how you should think. Gautham

  • @biplabipradhan6497
    @biplabipradhan6497 Před 8 měsíci

    Scenario 1 - Dormancy because here we are analysing the impact of delay Scenario 2 - Connectivity as risk is connected to other associated risk Scenario 3 - proximity as duration for impact of risk is identified Scenario 4 - Urgency as implementation of risk response plan is given in the scenario

  • @kafilahmad
    @kafilahmad Před 5 měsíci

    1. Dormancy because risk is realized and 3 mores are needed for simulation to asses the impact.
    2. Connectivity because many risks are connected to other modules
    3. Proximity because risk will start impacting the project within 30 days
    4. Urgency because risk response plan has to be completed within 20 days or risk will affect the project's objective

  • @osam_8004
    @osam_8004 Před 3 měsíci

    1-Dormancy
    2-Connectivity
    3-Proximity
    4-urgency

  • @ajithpaulisaac5074
    @ajithpaulisaac5074 Před 5 měsíci

    Scenario 2 is Urgency. Time when RRP to be implemented .

    • @EduHubSpot
      @EduHubSpot  Před 5 měsíci

      Correct Answer is Connectivity.
      Gautham

  • @pratikkumarbamm5642
    @pratikkumarbamm5642 Před 5 měsíci

    1. Domancy - As risk is realized and you need 3 more days to identify the impact 2. Connectivity - Risk is connected with lot of other modules so it has high connectivity 3. Proximity - It states that, risk is identified and it will start to impact the project in 30 days so it has 30 days proximity. 4. Urgency - After risk identification, you have identified risk response plan which will get implemented within 20 days. Thank you.

  • @monolekha
    @monolekha Před 6 měsíci

    Scenario 1: Dormancy; the impact of the risk can only be understood after the 3 days, so there's a wait time
    Scenario 2: Connectivity; the risk is connected to a lot of other modules and potential risks
    Scenario 3: Proximity; the proximity to the risk is 30 days as the risk will impact in 30 days
    Scenario 4: Urgency; the risk response implementation will take 20 days

  • @manimenon305
    @manimenon305 Před 2 měsíci

    1: Dormancy
    2:Connectivity
    3: Proximity
    4: Urgency

  • @dghavban
    @dghavban Před 5 měsíci

    1. Dormancy - (the risk has occurred)…..
    2. Connectivity(Connected to lots of modules)
    3. Proximity (start impacting within 30 days)
    4. Urgency(question has plan that needs to be completed within 20 days)

    • @EduHubSpot
      @EduHubSpot  Před 5 měsíci

      Keep up the good work !!
      Gautham

  • @user-ct7pn2yk9e
    @user-ct7pn2yk9e Před 8 měsíci

    scenerio1-Dormancy Scenerio 2 connectivity scenerio 3 - proximity scenerio 4 - urgency

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      Keep up the good work!! Gautham

  • @poojamakhijani688
    @poojamakhijani688 Před 8 měsíci

    Scenario 1 - Dormancy because you have to wait for three more days to implement risk response
    Scenario 2 - Connectivity as it is connected to other modules
    Scenario 3 - Proximity - as it has given the time within which risk will start impacting the project
    Scenario 4 - Urgency - as it mentions the time within which you have to implement the risk reponse plan.

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      Loving your thought process. Gautham

  • @yashtambe4263
    @yashtambe4263 Před 2 měsíci

    Scenario 1 - Dormancy ...Technical risk is already realized. and PM needs to wait 3 days to understand the impact of the risk, meaning how to solve the risk he will able to know after three days.. i.e. dormancy is 3 days
    Scenario 2: Connectivity ............. Technical risk is connected to lot of modules...
    Scenario 3: Proximity ............ Technical risk will start impacting from 30th days.. so we have 30 days to solve it... that is Proximity
    Scenario 4: Urgency ............. Risk response plan should be execute in 20 days...

  • @MrAkeem01
    @MrAkeem01 Před 8 měsíci

    Scenario 1: proximity
    Scenario 2: connectivity
    Scenario 3: Dormancy
    Scenario 4: Urgency

    • @EduHubSpot
      @EduHubSpot  Před 7 měsíci

      Scenario 1 - Dormancy - In this scenario, You must wait for three more days to detect the impact of the risk.
      Scenario 3 - Proximity - In this scenario, the risk will start to impact the project objectives within 30 days.
      2 & 4 is correct
      Gautham

  • @MarcoReyes-xe8hx
    @MarcoReyes-xe8hx Před 5 měsíci

    Scenario 1: Dormancy - the risk has occurred and will take 3 days to be identified.
    Scenario 2: Connectivity - the risk is connected to other modules.
    Scenario 3: Proximity - the risk will begin impacting the project within 30 days.
    Scenario 4: Urgency - the risk response plan has already been identified with an elapsed time of 20 days.

  • @subhrajitbera1655
    @subhrajitbera1655 Před 8 měsíci

    Scenario 1 Dormancy - the risk has already occurred and the time before the analysing the impact of the risk is 3 days.
    Scenario 2- Connectivity. The risk has an impact on a lot of connected project activities.
    Scenario 3 proximity - the risk has been identified and can impact your project within 30 days. That means the risk to be mitigated within 30 days.
    Scenario 4 - Urgency. The risk response plan needs to be implemented on or before 20 days

  • @dr.nailamahmuda5505
    @dr.nailamahmuda5505 Před 5 měsíci

    Senario 1 : Dormancy
    Senario 2 : Connectivity
    Senario 3 : Proximity
    Senario 4 : Urgency

  • @chetnajain6704
    @chetnajain6704 Před 5 měsíci

    Scenario 1: Dormancy cz u have to wait for 3 days to identify the impact
    Scenario 2: Connectivity cz technical risk is connected to a lot of other modules of software
    Scenario 3: Proximity cz the risk will start impacting the project in 30 days
    Scenario 4: Urgency cz the response plan has to be completed in 20 days

  • @ilanchezian822
    @ilanchezian822 Před 5 měsíci

    The Risk can make an impact is Proximity
    The Risk Response Plan must be impliment is Urgency

    • @EduHubSpot
      @EduHubSpot  Před 5 měsíci

      Correct Answers :
      Scenario 1 - Dormancy - In this scenario, You must wait for three more days to detect the impact of the risk.
      Scenario 2 - Connectivity - In this scenario, the risk is connected to other modules
      Scenario 3 - Proximity - In this scenario, the risk will start to impact the project objectives within 30 days.
      Scenario 4 - Urgency - In this scenario, the risk response plan has to be completed within 30 days. Here they are talking about the time to complete a risk response plan.
      Gautham

  • @vibhor305
    @vibhor305 Před 8 měsíci

    Proximity - Risk will start impacting the project within x no of days
    Connectivity - Risk is connected to other modules
    Urgency - Risk response plan has to be completed within X of days
    Dormancy - To identify the risk need x of days

  • @abhivicky741
    @abhivicky741 Před 8 měsíci

    Scenario 1 Dormancy. Scenario 2 connectivity. Scenario 3 Proximity. Scenario 4 Urgency

  • @user-ru9fw2bn1t
    @user-ru9fw2bn1t Před 8 měsíci

    Scenario 1- Dormancy - As it is mentioned that the risk is realized and its required to wait for analyzing the impact within 3 more days
    Scenario 2- Connectivity - The mentioned risk is connected to several other risk to implement the project.
    Scenario 3- Proximity - As this risk will start impact the project objectives in next 30 days
    Scenario 4- Urgency - As this risk talks about the implementation timeline of risk response plan
    Reply

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      That is exactly how you should think. Gautham

  • @parekhashwin7862
    @parekhashwin7862 Před 8 měsíci

    Scenario 1 - Dormancy : Impact of the Risk will be identified only after 3 Days
    Scenario 2- Connectivity : risk is connected to other modules
    Scenario 3 - Proximity : Risk will impact the project withing 30 days.. U have a 30 day to mitigate the Risk
    Scenario 4 - Urgency : Risk Ready plan is ready and need to completed in 20 Days.

  • @ifthekarhassan2114
    @ifthekarhassan2114 Před 7 měsíci

    1Dormancy
    2Conectivity
    4Urgency
    3Proximity

  • @somnathmazumder1713
    @somnathmazumder1713 Před 4 měsíci

    😂😂e😂E😂e3eEeeeeEaee333à❤3❤❤❤❤❤AWEÀAÀ3EE❤❤E❤WA❤❤

    • @EduHubSpot
      @EduHubSpot  Před 4 měsíci

      Thanks for loving the video.
      Gautham

  • @malinimarkasagayam2085
    @malinimarkasagayam2085 Před 8 měsíci

    Scenario 1- Dormancy - As it is mentioned that the risk is realised and we are waiting for analysing the impact within 3 more days
    Scenario 2- Connectivity - As this risk is connected to several other modules in the project
    Scenario 3- Proximity - As this risk will start impact the project objectives in next 30 days
    Scenario 4- Urgency - As this risk talks about the implementation timeline of risk response plan

    • @EduHubSpot
      @EduHubSpot  Před 8 měsíci

      That is exactly how you should think. Gautham

  • @arkaleem
    @arkaleem Před 8 měsíci

    Scenario 1 is Dormancy because a risk has been realized in order take action on the delay
    Scenario 2 is Connectivity because the risk has been identified to be connected with other works
    Scenario 3 is Proximity because the risk has been identified before its impact
    Scenario 4 is Urgency because the risk response plan has to implemented in order to avoid impact of the risk

    • @EduHubSpot
      @EduHubSpot  Před 7 měsíci

      That is exactly how you should think. Gautham

  • @anandagashe7065
    @anandagashe7065 Před 8 měsíci

    1-Dormancy
    2-Connectivity
    3-Proximity
    4-Urgency