How to Make the BEST Gantt Chart in Excel (looks like Microsoft Project!)

Sdílet
Vložit
  • čas přidán 2. 06. 2024
  • ⭐️⭐️⭐️ GET THIS TEMPLATE PLUS 52 MORE here: www.etsy.com/listing/11998005...
    👍 Ready made and ready to use.
    How to make the absolute BEST weekly Gantt Chart in Excel, that looks like Microsoft Project and is easier and better to use! Your managers and team will ask you "Where did you get this from?" and "Can I use it?" because it looks so good when you're updating your project.
    Features include: milestone diamonds, automatic Gantt chart bars, automatic counting number of working days, automatic percent complete on Gantt bars, coloured bars for complete tasks and for blocked tasks, and automatic calendar.
    Timestamps:
    00:00 Gantt Chart overview
    01:53 Getting Started
    02:31 Creating the Calendar
    05:26 Adding lines and borders
    06:40 Number of Working Days
    07:24 Status drop down list
    09:21 Adding milestone diamonds
    10:27 Adding the Gantt bars
    12:33 Adding the percentage complete on the bars
    13:12 Adding the complete golden colour
    14:03 Showing blocked items
    15:12 Freeze panes for scrolling
    #ProjectManagement
    All the Project Template Excel and Powerpoint videos: • How to Create Excel an...

Komentáře • 1K

  • @trustedconsultingllc9902
    @trustedconsultingllc9902 Před rokem +43

    David, you're a natural born teacher. Very much appreciate your positive and encouraging tutorial on how to do these things for yourself.

  • @j.c.7574
    @j.c.7574 Před 7 měsíci +390

    Here is the DAX for the video.
    Top row dates: =IF(MONTH(D3-WEEKDAY((D3),2)+1)=$E6-(WEEKDAY($E6,2)+1),K$40,K$4=$E6-WEEKDAY($E6,2)+1)
    Completed: =AND($H6="Complete",K$4=$F6-WEEKDAY($F6,2)+1)
    Blocked: =AND($H6="Blocked",$I6>0,K$4=$E6-WEEKDAY($E6,2)+1)
    Hope this saves future viewers some time!

  • @DubseditionTCG
    @DubseditionTCG Před 2 měsíci +13

    I can honestly say, my team was impressed when I whipped this out to present the other day

  • @shreyapandey376
    @shreyapandey376 Před 2 lety +55

    Simply amazing! I had no idea excel sheets could look so aesthetic. You've completely changed my life, this Gantt chart is a game-changer!

  • @jaredbarber7257
    @jaredbarber7257 Před 6 měsíci +4

    This video is fantastic and the presenter does an amazing job. David's enthusiasm is infectious and I honestly had fun making a Gantt chart for my project - never thought I'd say that!

  • @mikekennedy5843
    @mikekennedy5843 Před 3 měsíci +3

    Thanks David, this is one of the best tutorials available for Gantt Chart creation and Conditional Formatting

  • @meaningofmovementpodcast5996
    @meaningofmovementpodcast5996 Před 7 měsíci +2

    This is a straight-up amazing walkthrough on how to create a well functioning Gantt Chart. Thanks so much for sharing, it will be put to great use!

  • @odrazleinad
    @odrazleinad Před 2 dny +1

    Awesome video... applied many of the ideas for my project planner template. Thanks for the really useful content David.

  • @billgordy169
    @billgordy169 Před rokem +4

    David, you're making me look like a genius. This has been so informative and useful. Thanks so much for sharing.

  • @carolinewarren3587
    @carolinewarren3587 Před 3 měsíci +7

    Thank you, David, for an (almost) idiot-proof tutorial on creating a customized Gantt chart. It took me about 4 hours, but I'm thrilled with the result, and the fact that I can use this template for other projects in the future. Many, many thanks for your help!

  • @kasperraunholst
    @kasperraunholst Před 3 měsíci +1

    Such contageous enthusiasm. I love how a square becomes "a beautiful diamond". Thanks a lot for making this one.

  • @chantellelavie
    @chantellelavie Před rokem +19

    Excellent tutorial! Exactly what I was looking for. Thank you for taking the time to create and share it.

    • @nicholastugume1081
      @nicholastugume1081 Před 7 měsíci +1

      I am stranded at the addition of ghantt bars. what could be doing wrong

    • @agluglu8456
      @agluglu8456 Před 7 měsíci

      @@nicholastugume1081 i managed to do that, but i am stucked at the diamond milestone

    • @kunalpatil1776
      @kunalpatil1776 Před 5 měsíci

      @@nicholastugume1081 same, my ghantt bar isnt visible even after applying the right formula. Some formatting in the later part is not working too. Can someone help - what may be going wrong ?

  • @hamodeosso6507
    @hamodeosso6507 Před rokem +5

    Hands down the most straight forward and visually appearing GANTT chart

  • @Sali7691
    @Sali7691 Před rokem +4

    Absolutely amazing and much needed, I was looking for some advanced Gantt chart for. months, and here I got it, many thanks, considering buying your template, looking for some discount !

  • @user-xz3pp1nc5c
    @user-xz3pp1nc5c Před 10 měsíci +2

    Great job. I completed the Gantt chart and am very excited to implement it. You are excellent, sir!

  • @hettardsplat
    @hettardsplat Před 5 měsíci +7

    Fantastic step by step! Some of the bits went a little quickly so a LOT! of pausing and repalying but I now have an amazing Gantt chart to use across multiple projects! well worth the time invested.
    One suggestion would be to post the different formulas in the description to make it easier and save a LOT of typing and re-typing when things go wrong.

  • @Simon-jg4qf
    @Simon-jg4qf Před 11 měsíci +3

    Thank you David, this is incredibly useful as I am a civil engineering student at a university that does not provide access to MS Project regardless of the crazy fees that I'm paying 🤣

  • @DarthJ2164
    @DarthJ2164 Před rokem +6

    Absolutely great tutorial and explanation! Your positive energy has made me even more excited to start using this format. I will be updating my project timelines to this format! THANK YOU!

  • @martin3958
    @martin3958 Před 2 měsíci +1

    Your positivity has made excel bearable for me. Thank you

  • @ejvideos07
    @ejvideos07 Před rokem +1

    Oh my Lord !! This changes everything I do at work. I thought the answer was to use Charts, but this is so much better. Thank you.

  • @gelsondiaz198812
    @gelsondiaz198812 Před 10 měsíci +19

    Excellent work. This tutorial was very easy to follow and easy to implement. As a recommendation you could add the formulas on the description for faster Gantt chart creation and that way we can focus more on the explanation.

    • @dougmowbray2606
      @dougmowbray2606 Před 6 měsíci

      my thought exactly

    • @corneking5878
      @corneking5878 Před 4 měsíci +1

      I can't get any of the formulas to work, giving up. Wasted soooo much time trying. Will just buy a project software.

  • @docco6767
    @docco6767 Před 11 měsíci +4

    This is considerably better than the ones in my work. Thank you and your formulas actually work, unlike 90% of the ones on CZcams.

    • @PatchedBandit
      @PatchedBandit Před 4 měsíci +2

      Mine are not working though. "problem with formula"

    • @prodriver_es5647
      @prodriver_es5647 Před 2 měsíci

      @@PatchedBanditI need to change “,” to “;” and worked for me. Hope you solve that problem.

  • @AndreaUK1973
    @AndreaUK1973 Před 2 lety +2

    I’m so so grateful for your wisdom! Thank you ever so much! I can’t wait to start mine!

  • @sandrabiggerstaff8602
    @sandrabiggerstaff8602 Před rokem +1

    OK...this is amazing. Thank you for sharing you learning. I work in Project, but sometimes not everyone has project within an organization.

  • @holidays5476
    @holidays5476 Před rokem +11

    This is slick - thanks so much! Love your energy into the video. Going to use this for my next project.....people may think I know what I'm doing! :)

  • @AmitPatel-123
    @AmitPatel-123 Před rokem +3

    Amazing tutorial , i was able to successfully create a great tracker using this. Made few tweeks to highlight overdue items status box and remove highlights from gantt chart if status marked as not started. Again thank you so much for this great tutorial , subscribed

  • @user-km4ed1vp5p
    @user-km4ed1vp5p Před 3 měsíci +1

    What a Gantt chart! Really the best! Thank you so much, David.

  • @heshamhamoodalshaif9077
    @heshamhamoodalshaif9077 Před rokem +1

    Amazing, thank you! You taught me more in 16 minutes than my prof did in 4 weeks!

  • @Lilly_roblox_edits
    @Lilly_roblox_edits Před 2 lety +8

    Hi! I passed my PMP exam with above target in all three categories. Thanks for your videos!

    • @davidmclachlanproject
      @davidmclachlanproject  Před 2 lety +1

      That is amazing Linda, congratulations! You have conquered a very difficult task 🙂

    • @s2_p_2524
      @s2_p_2524 Před rokem

      @@davidmclachlanproject Hi David . Thanks for the video , was really helpful . How can I get this template please ? I tried creating it , but getting stuck at the end . Thanks 🙂

  • @coryrubino8007
    @coryrubino8007 Před rokem +3

    Thank you for the video, David! Your instructions made it so easy to replicate. Quick question for you. Is it possible to set an estimated completion date(set with diamond on the Gantt chart) for a task, but it fills in the weekly boxes with the corresponding color as the weeks go by? Essentially extending past the diamond in the chart until an actual completion date is entered?

  • @eljacoby
    @eljacoby Před rokem +1

    You have literally SAVED MY LIFE today with this!!!! Thank you!!!!!!!

  • @AbeerPervaiz
    @AbeerPervaiz Před rokem +1

    OMG! i Canno believe this but I made the GANTT CHART and its amazing! Thank you for this tutorial.

  • @dalilas5085
    @dalilas5085 Před 4 měsíci +3

    You are my life saver THANK YOU SO MUCH for the amazing content!!!!!

    • @dalilas5085
      @dalilas5085 Před 3 měsíci

      p/s my team are IMPRESSED with this ganttchart for real !!!!!

  • @leandros40
    @leandros40 Před 8 měsíci +3

    Excellent clip, thank you David! Very detailed and helpful. One question: is there a way to edit/ament the chart and have the months broken into weeks and the weeks into dates, and then by using the "Group" function under Date to collapse or expand the cells?

  • @Nicole-deluxe
    @Nicole-deluxe Před rokem

    Ridiculously good!! So well-instructed and helpful. Thank you!!

  • @jodyswartz2827
    @jodyswartz2827 Před 3 měsíci +2

    Thank you so much for this!!
    I've created a Gantt chart that my boss will be happy with for a company-wide project!
    ⭐⭐⭐⭐⭐

  • @jonstevens7269
    @jonstevens7269 Před 2 lety +5

    This is really good! Can you show how in this example -- John is ready for another task 16 May. How do you add that without losing the previous tracked task? That way, you could forward allocate tasks and the entire year would show a record of time allocation by team member. When the director asks "what have your people been working on all year?".

    • @prodriver_es5647
      @prodriver_es5647 Před 2 měsíci

      It is the same example I requested now hope David give us a tutorial or a template to buy with that issue. I really need it for planning tasks!!!

  • @barryluo2011
    @barryluo2011 Před 7 měsíci +12

    Hello David, thank you for the tutorial, any chance we can switch this into a tracking sheet by days instead of weeks? What are the things we need to modify based on this tracking sheet? Thanks in advance!

  • @julianwearne4967
    @julianwearne4967 Před 3 měsíci +1

    This is a top notch tutorial for a top notch product. Appreciate your efforts a lot here David.

  • @therealshaesantana
    @therealshaesantana Před 2 lety +1

    THANK YOU! Great video to help create an awesome looking and USEFUL gantt chart!

  • @johnsebastianrozofuentes5796

    I am a beginner and it took me about an hour. To be honest, I never thought I would make it, anyway I tried, and I actually made it.
    It wasn't that difficult because of the way you explained it all. Man, can´t thank you enough! blessings

    • @davidmclachlanproject
      @davidmclachlanproject  Před rokem +6

      An hour, that's impressive! It took me about a week after work to figure out all the bits and pieces, so: time saved 🙂

    • @yourfatherofyourmother2035
      @yourfatherofyourmother2035 Před rokem

      @@davidmclachlanproject can you please give us the functions for day per day ?

    • @faseehaneil3809
      @faseehaneil3809 Před 10 měsíci +1

      ​@@davidmclachlanprojecthey David I'm making this right now, an absolute beginner here. I just don't get how to like get that calender thingy. I mean the rows and columns size and height after I how to do that?

    • @Safari_Secrets.
      @Safari_Secrets. Před 8 měsíci

      @@yourfatherofyourmother2035 Did you ever find out

  • @ianlynch3594
    @ianlynch3594 Před 8 měsíci +5

    Hi David, great Gannt chart and very easy to follow and develop, just wondering is there an easy way to make the date dependant?

  • @kevenc
    @kevenc Před 11 měsíci +1

    Clearly you are an Excel time genius! Thanks!

  • @michaelcupito6832
    @michaelcupito6832 Před rokem +2

    David, you're amazing. Thank you so much for this. I'm going to put the video on super-slow-motion with my mouse hovering over the pause button and see if I can recreate something like this to fit my needs 🙂

  • @Deitzable
    @Deitzable Před rokem +7

    For the Milestones, none of my conditional formatting is working when plugging in the formulas, and the wingdings aren't showing up. Need help!

  • @TKtotheMax
    @TKtotheMax Před rokem +3

    Hello, thank you for showing us how to do it. would it be possible to copy the formulas into the description so we can copy and past them in and change the cell references. I have tried to type up the formula into the cells and I keep getting error messages. It says it is too long to even try the first one. Thank you

  • @paulocovele6091
    @paulocovele6091 Před 5 měsíci

    Thank you so much David. You saved my life. I appreciate your way of teaching

  • @EliramNoamOzmos
    @EliramNoamOzmos Před rokem +1

    This is absolutely phenomenal. Great job.

  • @paulkelly6446
    @paulkelly6446 Před 2 lety +5

    Nice work. I added the following formula and named range to the ID# so that deleting a task renumbers and keeps the tasks id in order =IF(ROW(id)=ROW($B$5)+2,1,MAX(prev_col_range)+1) named rage id = $B5 and named range prev_col_range = $B$5:B4

  • @natassakazepidou6639
    @natassakazepidou6639 Před rokem +22

    great video; may I ask if you provide the formula where you use to format the dates across the year?

    • @robertduda4234
      @robertduda4234 Před 11 měsíci

      I think you are asking about 2 consecutive calendar years:
      How do you sort by start dates if your project spands TWO years?

  • @simondavis2116
    @simondavis2116 Před měsícem +1

    I'm currently undergoing a Site Management course. I've been banging my head against the wall trying all sorts of formulas to get this right. This is by-far one of the best examples of a self-build Gantt Chart, and has become indispensable to me! Many Thanks, David!
    P.S. I've managed to manipulate a formula to introduce and over run on any particular task! Again Thanks David!

  • @carlo9567
    @carlo9567 Před rokem +1

    Clear and simple. Great job !

  • @robertduda4234
    @robertduda4234 Před 11 měsíci +4

    May I suggest that we organize (organise) a project to incorporate some / all of the desired features:
    • Critical Path Analysis
    • Dependencies of Activities
    • Resources Loading
    • "What if" scenario calculations
    • Resource leveling / smoothing
    • Unexpected loss / delay of a resource

  • @hmnc444
    @hmnc444 Před 2 lety +6

    Its crazy how you manage to use excel to create such a complex and useful gantt chart. I can barely get my formatting to work hahaha. Great stuff.

  • @teresafahy2073
    @teresafahy2073 Před rokem +2

    Thank you so much David, this has taken me a couple of weeks to complete but now that I have I will keep it forever. It truly is the best Gantt chart I have used and it shows clearly everything any looking at my chart needs to know. So grateful!👏👏👏👍🙂

    • @naheemrazwan
      @naheemrazwan Před rokem +1

      how did you create the same exact sized calendar boxes, thats the only thing I couldn't figure out, rest was absolutely amazing :)

    • @teresafahy2073
      @teresafahy2073 Před rokem +1

      @@naheemrazwan Hi Naheem, I had to do this part manually as I wasn't able to see how it was done any other way. I just moved the curser on the lines between each date box to 2.50 and once you've done a few, then highlight these cells and using the cross move it across to the number of cells you need and it will automatically adjust these to 2.50 also. You will need to do this before merging the cells with the names of the months. This was something David didn't show in his video, but I had done it before. It really is a great Gantt chart and I've been able to pass it on to others in my team. However I locked the cells containing the formula's so anyone else using it can update the information but not change the formula's in the actual chart. Good luck, I hope it works for you.

    • @baileyanderson7551
      @baileyanderson7551 Před 9 měsíci

      Were you able to insert the milestone diamonds? I have copied the formula numerous times and I cannot seem to get the diamond to show up. As I watch the video it appears he has clipped the video before explaining further?@@teresafahy2073

    • @nishantkambli
      @nishantkambli Před 2 měsíci

      Heyy does your sheet work perfect?

  • @rafaelcdionisio
    @rafaelcdionisio Před rokem +1

    Your videos are amazing, they help me a lot in work and school. great work!

  • @joshualederhandler6157
    @joshualederhandler6157 Před 2 lety +3

    Great video, thank you! If I want to take the individual days timeline and turn them into weeks across a month, how could I do that?

  • @steffipullely6907
    @steffipullely6907 Před 2 lety +13

    Hey David, just wanted to say that I love what you created. I wanted to ask if you have expanded any further using Gantt charts on excel? For example adding in a critical path or milestones, keeping track of budget used in each phase etc

    • @morristheman1848
      @morristheman1848 Před 2 lety +1

      Would love to see this as well! Let me know if you found somewhere else to do this

    • @ksojoel
      @ksojoel Před rokem +1

      that would be awsome, since the critical path is.. well.. CRITICAL in any project

  • @Nadiapm2001
    @Nadiapm2001 Před 10 měsíci +1

    Thank you so very much! I feel so proud of myself...courtesy of your shared wisdom and insane Excel skills!

  • @kirandesai68
    @kirandesai68 Před rokem +1

    Absolutely brilliant, mate. Thank you so much. I learned so much from this.

  • @MRMOTOFOTO
    @MRMOTOFOTO Před rokem +4

    Took me 4 hours...lol, but that was great. Thanks!!!

  • @paolamorales2751
    @paolamorales2751 Před 2 lety +4

    Do you have a tutorial on how to add dependencies between tasks? Great video!

  • @officetricks6303
    @officetricks6303 Před 2 lety +1

    Insanely helpful and clear. Thank you for sharing this...

  • @Rhitalbaldwin
    @Rhitalbaldwin Před rokem +1

    SUPER HELPFUL!! One thing, as a new learner, I did not realize that the formulas you are plugging into the formatting don't exist in any cells yet.

  • @dagwould
    @dagwould Před rokem +4

    A couple of thoughts: drop down lists maybe on a separate 'tools' sheet: easier to use across tabs and to update. Use a table for the list. % complete only for when the output is countable. Estimates never work. If there is no countable output, the activity is 0% until it is 100%. And 100% means accepted by the PM (and the client). IMO, better to have an expected completion date, so it is concrete and drives commitment on the reporter.

    • @davidmclachlanproject
      @davidmclachlanproject  Před rokem +1

      These are great ideas, certainly do-able 🙂

    • @dagwould
      @dagwould Před rokem +2

      @@davidmclachlanproject David, glad you found my thoughts of interest. One more thought, in my domain, a milestone is a durationless event; I identify a milestone as an activity of zero duration: so start and end dates are the same. They usually come at the end of a sequence of activities that produce a work package or discrete component.

  • @sainimadhur
    @sainimadhur Před 2 lety +6

    Hi @David,
    Great work. How can we break down the timeline from weeks to days. Your inputs will be really helpful. Thank you for the video. 🙏

    •  Před rokem

      @David, answer please to this question

    • @aerolleameermitra1630
      @aerolleameermitra1630 Před rokem

      Do we already have an answer for this? 🙏

    • @vcanadian1971
      @vcanadian1971 Před rokem +1

      Instead of +7 change to +1

    • @jimmietraylor7413
      @jimmietraylor7413 Před měsícem

      @@vcanadian1971 The conditional formatting formulas need to be changed as well.

  • @samglover2708
    @samglover2708 Před rokem +1

    This is absolutely outstanding and exact what I was looking for. SUBSCRIBED!

  • @richardwalton3613
    @richardwalton3613 Před rokem +12

    Well done. Though it is missing a key component of a gantt chart: Dependencies. The whole purpose of a (complete) gantt chart is to show what tasks depend on what other tasks and what the impact of changing one or more tasks has on the schedule. If your intention was artistic in nature, this is very good. But don't sell this as a gantt chart.
    Thanks for showing how to build our own sheets. Much more impactful than simply uploading someone else's sheets.

    • @southcoastsynthesis
      @southcoastsynthesis Před rokem +1

      I agree. The point of using a tool like MS Project is for predecessors and successors and the whole scheduling engine. Also, summary tasks and other features for navigating a large project schedule. Not to mention resourcing features. Excel might be OK for a very simple task list but I can't imagine running an actual project without something like MS Project!

    • @robertduda4234
      @robertduda4234 Před 11 měsíci

      See my question about the FOUR types of dependencies.

    • @danielbarnatt9332
      @danielbarnatt9332 Před 7 měsíci +3

      I think how important this is depends on the size of the project, Many mini projects can and are managed on excel sheets manually and this automates some of the basic functions of laying out a chart. I find managing an ms project plan cumbersome in pretty much all but the most rigidly defined projects. Equally i often find faults in the ms-project scheduling engine that can put your entire plan out of kilter, meaning you up end spending more time getting your plan to behave correctly than you do actually delivering anything. In the kind of environments i manage manage projects in i need something that is quickly editable on the fly at a whim, without being to concerned with what impact changing one line may have on the rest of the plan. I can make notes against the cells in excel and cater for the dependencies later when i have time. Also in complex changing environments dependencies are always changing , and often things that you thought were dependencies turn out not to be and vica versa. In my experience having a plan that is a little looser in is restrictiveness can actually be helpful for a busy project manager.

    • @jamessbca
      @jamessbca Před 4 měsíci

      @@danielbarnatt9332this has been my experience as well.
      Any MS project schedule I create is like a beautiful work of art on Day 1. But I’ve never successfully tracked progress in it.
      I’ve been developing a “task list” in excel that simply has tasks, estimated hours per task, and a “percent complete” cell, which drives 10 conditionally formatted cells that represent a “gas gauge” - how close to done the task is,
      From 1-10
      Real life is always way more complicated than an MS project schedule.
      The fact that project doesn’t let me take notes anywhere on the screen just kills me.
      I’m reinvigorated with the idea of doing this in excel (and keeping it very simple) due to recently working with a very competent project manager who uses a white board and post-it notes. He doesn’t use a computer at all, let alone MS project.
      (And I just save the excel file with a new date in the filename each time, so I could always go back in time super easily if I ever wanted to…)

  • @mickholgate3347
    @mickholgate3347 Před rokem +4

    Hi David, hope you are open for development suggestions, if so @1:22 when you select complete, the progress should ideally default to 100%.

    • @vcanadian1971
      @vcanadian1971 Před rokem

      I agree…what formula would you recommend?

  • @JesusPerez-sv7ki
    @JesusPerez-sv7ki Před 4 měsíci +1

    You're amazing! Thanks for sharing your knowledge. You're so kind.

  • @user-mf8dm8gk5d
    @user-mf8dm8gk5d Před rokem +1

    You are amazing, thank you so kindly for taking your time to share this tutorial.

  • @conoromelia8435
    @conoromelia8435 Před 2 lety +3

    Very very impressive chart. Im 100% going go make one, its 100% going take me hours to do though 🤣

    • @davidmclachlanproject
      @davidmclachlanproject  Před 2 lety +3

      It took me two weeks to figure it all out and put it together, but I am not the fastest person 😂

    • @conoromelia8435
      @conoromelia8435 Před 2 lety

      Im a project manager and that chart is going to become part of my arsenal. Thank you!

  • @chloehugaga2203
    @chloehugaga2203 Před 2 lety +8

    Thanks for such wonderful video, but I failed to do the today’s bar. Tried few times with the possibilities on my understanding. Can u teach again on where should I type the formula? Thanks

    • @ibd991
      @ibd991 Před rokem

      Same place i got stuck because if I put the formular it gives me error. Did you find a way around it?

    • @chloehugaga2203
      @chloehugaga2203 Před rokem

      @@ibd991 yes. I found the solution. how about you?

    • @suzanneocchipinti6318
      @suzanneocchipinti6318 Před rokem

      @@chloehugaga2203can you please share it?

  • @bhavitta
    @bhavitta Před rokem

    OMG This is amazing.
    Thank you so much for these thorough cool tips to make this semi-automated gantt chart. Awesome !!!! 🎉🎉🎉🎉🎉🎉

  • @AMindInOverdrive
    @AMindInOverdrive Před rokem +1

    This is exactly what I was looking for! Thanks a million!

  • @declanhutchings573
    @declanhutchings573 Před rokem +31

    @David McLachlan if you add this code into it =IF(ISBLANK($B6),TRUE, FALSE) into a rule with the right fills and what not it can hide cells, not in use until task number is add to make it look even cleaner

  • @ipm131
    @ipm131 Před rokem +4

    Hello and thank you for this video. I am having an issue with trying to get the Gantt bars, the formula =K$4=(TODAY()-WEEKDAY(TODAY(),2)+1) comes back as FALSE. And I am also confused about whether I'm replacing the formula for the weeks in K4 with this one.

    • @jermainepitter2001
      @jermainepitter2001 Před rokem

      Great question, having the same issues.

    • @sandropegado7462
      @sandropegado7462 Před rokem

      Great question. Having the same issue.

    • @ddothill
      @ddothill Před rokem +1

      The Gantt bar formulae need to be entered as Conditional Formatting rules. If you've created all the dates in row 4, and all the row data you are using in columns C to I, then you need to click on cell K6, then press Ctrl+Shift+End and it'll highlight the range of cells you are testing.
      Up on the Home menu, click Conditional Formatting, New Rule... then select the bottom rule type "Use a formula to determine which cells to format", enter the formula in the box below, set the Format... you want. Click OK, then Apply, then OK.

    • @ManjitKaur-fd1jb
      @ManjitKaur-fd1jb Před rokem +2

      Great video, yes I am having the same issue - please help

  • @user-ce1qm8lo8t
    @user-ce1qm8lo8t Před 7 měsíci

    Thank you very much for the tutorial! My head is already aching from working on this Gantt chart. My boss has been requesting it for weeks.

  • @SusanneWatson100
    @SusanneWatson100 Před 6 měsíci

    Simply brilliant. This was the literally fun to create. Much gratitude!

  • @brittneyjasmin
    @brittneyjasmin Před rokem +6

    Stuck on the step around 9:40 - making it show a u when that date falls within the week selected above. the formula isn't showing any errors and appears to be pulling from the right places but I am not getting the u on the week it should appear (the end date is 4/30/2022 and it should appear in the work week of 25-Apr). I even tried changing the end date to match the week day exactly and it doesn't seem to want to work. Anyone have any tips / advice?

    • @Gibraltariano
      @Gibraltariano Před rokem

      Hey, did you get an answer or resolve yourself? I also can’t get the symbol to appear.

    • @feeldulfo9387
      @feeldulfo9387 Před rokem

      manually add the formula, also do the fancy thing formula he said right at the beginning when he just start adding the day and month e.g., 22-Sep

    • @settyc
      @settyc Před rokem

      Work Around: I inserted a Column for Week Number for the End Date and used this formula =IF($G5-WEEKNUM(L$4)=0,"u"," ")

  • @brookepittman8505
    @brookepittman8505 Před 2 lety +21

    This is a great video but for us beginners it goes a little fast. I wish it was a little more broken down in the formatting portions and adding the tasks and stuff. Overall still a great video.

    • @bexwhiting81
      @bexwhiting81 Před rokem +4

      Agree. Great video but for a beginner, formatting the cells went way too quickly.

    • @robertduda4234
      @robertduda4234 Před 11 měsíci

      You tube allows for playback down to 25% to 75% of normal.

  • @hemanbassi12
    @hemanbassi12 Před 4 měsíci +1

    Thanks, David! Despite the availability of other tools, I felt compelled to give this one a try. I've just forwarded my Gantt chart to my supervisor.

    • @KonfliktZW
      @KonfliktZW Před měsícem

      Hi can I have the completed gannt chart please..I can't get the formulas to work

  • @MatthiasLeimbach-tj2wm

    You, Sir are one of my favorite human beings!

  • @IrishBoySF
    @IrishBoySF Před 2 lety +3

    I was following along fine and then once I got to the milestone integration and with the formulas I got lost. I have tried placing in the exact formula to no avail so I can't go any further with the GANNT creation. :-(

    • @davidmclachlanproject
      @davidmclachlanproject  Před 2 lety +2

      One thought: if you're not using the "fancy" start date formula, make sure your project date starts on a Monday. This should work with the rest of the formulas!

    • @IrishBoySF
      @IrishBoySF Před 2 lety

      @@davidmclachlanproject I tried changing the start date to Monday and it still doesn’t work. It’s a shame I really like to look at this chart but I can’t go any further. I spent a few hours designing this and now I can’t use it

  • @frederikloumann
    @frederikloumann Před rokem +4

    Hi David, great tutorial!
    Do you know why excel returns "there's a problem with this formula", when I e.g. try and run IF(K$4=($F6-WEEKDAY($F6,2)+1),"u",""). The same also goes for the following formula when trying to add the gantt bars? Best regards

    • @Gowaz89
      @Gowaz89 Před rokem +1

      Try using " ; " instead of " , "
      That worked for me

  • @myusernamesucks12
    @myusernamesucks12 Před rokem +1

    David, Thank you very much. was able to make this from the tutitorial. Really appreicated. Please keep them coming!

  • @ottertubetv9356
    @ottertubetv9356 Před 7 měsíci

    Thank you so much for the vid again. I was able to generate a daily based version of the spreadsheet by following your tutorial, this is going to be mighty helpful

  • @ClipPixie
    @ClipPixie Před 2 lety +16

    How can I download this

  • @davidc8392
    @davidc8392 Před rokem +5

    Here's that long formula for anyone that wants to copy and paste instead of taking 30min to try and write it down like me haha
    =IF(MONTH(D3-WEEKDAY((D3),2)+1)

    • @johanaxeback
      @johanaxeback Před 11 měsíci

      I'm afraid it did not work for me to just copy paste the formula.

    • @johanaxeback
      @johanaxeback Před 11 měsíci +1

      Problem solved :-) Human error from my side of course.

    • @finventureschannel
      @finventureschannel Před 7 měsíci

      I get and error at ,2. Somehow formula loses D3 after that.

  • @raulherrera83
    @raulherrera83 Před 10 měsíci

    Great tutorial! Thanks for the clarity slow pace and disposition!

  • @Dr.RiccoMastermind
    @Dr.RiccoMastermind Před rokem +1

    Really impressive, want immediately start rebuilding. Thank you so much!!

  • @herminiogarcia4303
    @herminiogarcia4303 Před 2 lety +5

    In my opinion, it is the best timeline chart I have ever seen. I need a help on the "Percent Done". The formula of the Percent Done on the Bar does not work for me: =AND($I6>0, K$4 = $E6 - WEEKDAY($E6, 2)+1). Shows an error. Help me!

    • @Hogidibi
      @Hogidibi Před rokem +1

      I'm getting the same :(

    • @jacobashdown8876
      @jacobashdown8876 Před rokem

      same

    • @jessicakahanek3845
      @jessicakahanek3845 Před rokem +2

      He never responded did he?
      I'm stuck on the same thing.

    • @swapnilkadam6641
      @swapnilkadam6641 Před rokem +2

      I think that's where almost everyone got stuck...is he going to respond on it or not?

    • @pietercharle8055
      @pietercharle8055 Před rokem

      had the same but resolved it this way:
      Added a closing parenthesis for the WEEKDAY function before the +1 in the second argument.
      Changed the greater than or equal to sign (>=) to just the greater than sign (>) in the third argument.

  • @angelinamendivil6083
    @angelinamendivil6083 Před rokem +2

    This is sooo cool! Thank you so much for sharing your knowledge and expertise :)

  • @TheHealingCorner-jk9yb

    best video, got praises from all of the team members, AWESOME VIDEO.

  • @honeytolani4521
    @honeytolani4521 Před rokem +3

    You should explain the formulas as well in depth.. it made it very fast.. super difficult to learn for a beginner

  • @manfvedi_unofficial7548
    @manfvedi_unofficial7548 Před rokem +31

    FORMULAS STARTED WORKING by replacing "," with ";"

    • @JoJoKaat
      @JoJoKaat Před rokem +1

      I can’t get the formula to work any further than the first square

    • @robertduda4234
      @robertduda4234 Před 11 měsíci +2

      Perhaps we need to perform a Risk Register entry and assessment to determine root cause analysis. lol

    • @dylpicklethebugslayer
      @dylpicklethebugslayer Před 8 měsíci +1

      Nope it doesn't work for me

    • @Kevin.7.
      @Kevin.7. Před 8 měsíci

      Mine display "#VALUE!" Did anyone find a solution?

    • @brianperkinson3354
      @brianperkinson3354 Před 6 měsíci +1

      Issues with formulas. I tried both (initial month and days) and none of them seem to work properly. A waste of time

  • @dsacweb
    @dsacweb Před rokem

    Thank you for the quick and positive reply. Thanks also for an excellent tutorial, I have found it invaluable.

  • @johnvodopija1743
    @johnvodopija1743 Před 9 měsíci +2

    I keep returning to this video even though I have followed along and recreated the template myself as a learning exercise. I have created a daily version for a more detailed view but use the weekly version to provide an overview. Simply superb! Thank you again. 👍😃

    • @khuloodal-alawi6907
      @khuloodal-alawi6907 Před 9 měsíci

      =IF(K$4=($F6-WEEKDAY($F6,2)+1),"u","")
      this one didn't work for me
      how to fix that

    • @summajae
      @summajae Před 8 měsíci +1

      Hi there! I'm looking at a daily version as well, but for some reason the =IF(K$4=($F6-WEEKDAY($F6,2)+1),"u","") formula doesn't work in the daily version. It works for 3 rows but the rest are a few days out. Did you use a different formula to place the diamonds on the gantt? Thanks!

    • @webdev3730
      @webdev3730 Před 8 měsíci

      @@summajae intriguing, i have come across the exact same issues. maybe its a version of excel thing??? mine do not work at all

    • @jimmietraylor7413
      @jimmietraylor7413 Před měsícem

      I am trying to set one for daily tracking as well but am having issues getting the conditional formatting formulas figured out. Any way you can provide those?

  • @richarddoncaster3275
    @richarddoncaster3275 Před rokem +15

    🙃 He purposely skips a few steps - so that you eventually give up and purchase the template.

    • @MrNavjodh
      @MrNavjodh Před 7 měsíci +1

      If you purchase the template maybe you will not learn

    • @CreatingWealth_
      @CreatingWealth_ Před 6 měsíci

      Exactly my thoughts Richard... Not any easy step

    • @davidcoad227
      @davidcoad227 Před 4 měsíci

      He put the work into it. If he wants to charge for the template, it’s up to him. He gave us enough information to still make it work.

    • @Lioness_UTV
      @Lioness_UTV Před 4 měsíci

      I think its fair to pay for the template as he created it.

    • @unluckymushroom
      @unluckymushroom Před 4 měsíci +1

      I honestly didn’t get the feeling… I followed the steps and copied the formulas and everything works smoothly 👌🏼

  • @brucealway2565
    @brucealway2565 Před rokem +1

    easy build, great instructions and a clean outcome .