  • This evolution uses one Engine Company and four members, one supply line, the 2 ½” with smooth bore and an apartment pack with nozzle. This timed evolution begins when the Engine stops at the designated fire area and airbrake applied.
    Standard requirements:
     The Engine stops at the designated fire area (near hydrant), and members in full PPE and SCBA (mask not worn).
     The Engine Company FF #1 stretches the 2 ½” preconnect and shows water.
     The Engine company FF #2 grabs the apartment pack and brings to FF #1.
     FF #1 shuts down the line, screws off the tip (places tip safely in pocket)
     FF #2 attaches apartment pack to the smooth bore. FF#2 stretches the line and calls for water.
     FF #1 let’s pump operator know extended line is added on to adjust pressures, FF #1 opens the bail.
     FF #2 shows water.
     Pump operator must account for friction loss and adjust pressures accordingly.
     The Engine operator secures the water supply from the hydrant to the apparatus.
     Time stops when handline has adequate pressure and water supply is secure.
    Recommended maximum time for the evolution is 4 minutes.