    In This video i have explained the Right Method for Placing of Lapzone in Beam Reinforcement, OR Lapzone in Beam Reinforcement. In this Video you get the technical details of Beam Reinforcement lapping Zone according to IS 13920.
    Reinforcement Lapping Zone in Beam
    Lapping Zone in Beams
    Lap Length Formula for Beam Reinforcement
    #BeamLapzone
    #FactualCivilEngineering

Komentáře • 87

  • @FactualCivilEngineering
    @FactualCivilEngineering  Před 5 lety +5

    Further if you have any query / questions, Please comment

    • @SUJITHPAYANDATH
      @SUJITHPAYANDATH Před 4 lety

      The situation of maintaining lapping zones asper the codal provisions will be difficult under situation of providing dowel bar for longer span beams,where we need to cast the beams later stage of project.The couplers are very useful under these situations.
      Also wastage of reinforcement bars will be higher for maintaining lapping zones asper IS codes.I prefer to cut the reinforcement bars of the following lengths 3m,4m,6m,8m

    • @alexanderodo3802
      @alexanderodo3802 Před 3 lety

      No English here

    • @sambathkumar003
      @sambathkumar003 Před 2 lety

      Sir, video 8:48 clause 4.4.1 and other clause not mentioned which IS code please tell me it will help me.

    • @trendingbastard9665
      @trendingbastard9665 Před rokem

      Sir aapki sab video technical hai bahut achhi se samjate hai aap Please aap jyada se jyada video banate jao tx sir

  • @mohammadshoeb4539
    @mohammadshoeb4539 Před 5 lety +8

    Really sir, you have fantastic knowledge of this field, lovely video full of knowledge thx

  • @VAIBHAVSPAL
    @VAIBHAVSPAL Před 5 lety

    Thank you sir,Kafi aacha samjha dia,Kafi kam time main...🙏🙏

  • @amitabhjaiswal9365
    @amitabhjaiswal9365 Před 5 lety +1

    Great sir, your video is diff. Bcoz u always make video with ref to is codes

  • @Chamle_Akin
    @Chamle_Akin Před 3 lety

    Came to the right place to clear my doubts. Thanks

  • @ankitsingh-mt3ti
    @ankitsingh-mt3ti Před 3 lety

    Thanks for making this Vedio thanks

  • @ManojKumar-gt4ct
    @ManojKumar-gt4ct Před 3 lety

    Very good explanation sir
    Your trick is so good to explain anything .

  • @RohitSharma-fg4zw
    @RohitSharma-fg4zw Před 2 lety

    🙏 great knowledge

  • @Coolguy4u
    @Coolguy4u Před 28 dny

    Don’t use 6m for your ease. Try using beam length 3.2m beam depth 450mm with 20mm rebars used as main rebars and 8mm as stirrups. Then you will realize the cons and its difficulty. Although whatever you said is true but sometimes in certain cases it is not feasible as the lapping zones seems to coincide almost within the same zones

  • @vikrantkumarsah
    @vikrantkumarsah Před 2 lety

    Best Deep Knowledge explaination

  • @irfanramdani5654
    @irfanramdani5654 Před 4 lety +2

    Good work friend

  • @sanjayborge2240
    @sanjayborge2240 Před 5 lety

    sir great information on great factual things on this uploaded video.regards.

  • @vikasdalal5854
    @vikasdalal5854 Před 5 lety +1

    Thank you so much sir, it's very important point

  • @devcpwd
    @devcpwd Před 2 lety

    Excellent

  • @dulhapur
    @dulhapur Před 3 lety

    Clear Height between plinth beam top and roof beam bottom-11 feets
    Zone-A-11/4=33 inches
    Zone-B-11*12-66=132 -66=66 inches
    There are 6 bars 16mm@4,12mm@2
    At zone B top- 2 no of lappings
    At zone B middle(30 inch below top lapping points)-3 no of lapping
    At Zone B bottom (30 inch below middle lap point)-1 lapping
    Whether the above arrangement is allowble?
    Whether lintel tie beam can be provided any zone?
    What if lintel tie beam falls on zone-A top area?

  • @miteshparmar2015
    @miteshparmar2015 Před 2 lety

    Narayan Bless 🙏 You

  • @manojkumar-pb7mh
    @manojkumar-pb7mh Před 2 lety

    Super Sir

  • @HarshitKS1618
    @HarshitKS1618 Před 5 lety +1

    Thank you sir, you should open an institute for site engineers. I'll pay you 1Lakh for this knowledge 😁

  • @nitinjain3612
    @nitinjain3612 Před 5 lety

    Nice video sir .good very good

  • @himalayadutta8158
    @himalayadutta8158 Před 2 lety

    You are god 🙏

  • @gulammohammed6476
    @gulammohammed6476 Před 4 lety

    Thanking you sir giving us to good knowledge....
    So plz make video on mix designs
    How to calculate cement sand and aggregates in 1m3

  • @MP-ug8up
    @MP-ug8up Před 3 lety

    Great information sir thanks for sharing,what if one beam crossing perpendicular to each other but no column below junction

  • @manishgupta6378
    @manishgupta6378 Před 3 lety

    Nice 👍 sir thank you 🙏

  • @chandreshkushwaha1456
    @chandreshkushwaha1456 Před 5 lety +1

    Maja aa gya sir

  • @MP-ug8up
    @MP-ug8up Před 3 lety

    Sir please clear last important point that you have said,you will clear in the next video, waiting for your video's

  • @adityavidwat4258
    @adityavidwat4258 Před 11 měsíci

    ❤❤

  • @jitpe3510
    @jitpe3510 Před 3 lety

    Hello Mr. Amitji ,
    Please make videos on Excavation for deep foundations near adjacent structures, safety and shoring details , soil investigation , Control Blasting .
    Thanks.

  • @asrbenatural6381
    @asrbenatural6381 Před 3 lety

    Would love to have MEP rate analysis, Costing and measurement video from you.

  • @jvvinay444
    @jvvinay444 Před rokem

    Plz explain lapping for slab n raft in same manner

  • @VAIBHAVSPAL
    @VAIBHAVSPAL Před 5 lety +4

    Some missing points.IS 13920 FOR BEAM CASE.
    1.The Factored axial stress on the member under earthquake shall not exceed 0.1fck
    2. The width of the member shall not be less then 200mm.

  • @hemantasingh8606
    @hemantasingh8606 Před 3 lety

    Sir for 20 feet span 6 no's 16 mm rod is used in beam for g+2 house .In between 20 feet distance pillar one small pillar of 4 no's 12 mm resting on underground beam also provided just 6 feet away from centre pillar ..it is ok or need to add more steel.?beam depth 14inch +6 inch slab thickness.column is 4 no's 16 mm &4 no's 12 mm

  • @bhaveshvinzava4794
    @bhaveshvinzava4794 Před 4 lety

    Apne Kaha Beam Ki width or depth ka ration...... .3 or .4 ke bich me hona chhahiye... To beam ki depth with slab gini jayegi.... Ya without slab

  • @sukeshdutta2333
    @sukeshdutta2333 Před 3 lety

    Good morning Sir, Is improper position of bottom bar lapping in beam can crack the underneath brick wall in future?

  • @mohdyusuf6819
    @mohdyusuf6819 Před 5 lety

    Sir ur explanation is good
    But please improve voice quality

  • @santoshkumar-id2oi
    @santoshkumar-id2oi Před 5 lety

    Good evng sir, ek video aap false ceiling ke measurement per bhi banye, with cove and without cove.

  • @ashujain206
    @ashujain206 Před 5 lety +1

    Please make a video for Overlap length kya lo gai for billing k liye. (One floor pr)
    1)Over lap 32 Dia se reduce ho kr 25 mm ho gya .
    2) over lap 25 Dia se increase ho kr 32 Dia ho gya .

    • @vikasv142
      @vikasv142 Před 4 lety

      Aise cases may always take d as your smaller Dia of bar and rest things are same .koi special Ld nahi Hoti hai bar ki dia. Change ho to refer IS 456 2000 U WILL HAVE BETTER KNOWLEDGE

  • @ankushnowal
    @ankushnowal Před 4 lety

    Sir where should laps be given in a beam resting on firm ground. For example a plinth beam resting on pcc.

  • @MdAdil-eg9jt
    @MdAdil-eg9jt Před rokem

    Please explain the in the beam of 14mtrs span

  • @sanjayborge2240
    @sanjayborge2240 Před 5 lety

    sir,please upload about the Right Method for Placing of Lapzone in Column Reinforcement.regards

  • @Getin2WiTank
    @Getin2WiTank Před rokem

    Dear Sir the Clause No. 4.4.1 you referred in the video is from which code ?

  • @aakashgoyal3899
    @aakashgoyal3899 Před 3 lety +1

    सर यदि बीम का क्लियर स्पान 5 मीटर हो और बीम 700mm डेपथ हो और उसमें 20 एमएम का सरिया लग रहा है तो फिर उसमें किसी प्रकार की कोई जगह ही नहीं बचेगी। उस कंडीशन में क्या करेंगे

    • @FactualCivilEngineering
      @FactualCivilEngineering  Před 3 lety

      Kya aap drawing ko share kar sakte h..my mail id is amit.ggn277@gmail.com, so that I can provide better solution / technical answer

  • @subscribefornoreasonplease9863

    How to find development length at beam to beam for connecting

  • @AmitKumar-fj2ih
    @AmitKumar-fj2ih Před 5 lety

    Sir top me sare lapping center me hi hogaye..

  • @madanlalsaxena6226
    @madanlalsaxena6226 Před 4 lety

    Sir tell us about lap length for welding a steel bar.

  • @shikhaverma9094
    @shikhaverma9094 Před 5 lety +1

    Sir if lap length fully cover inside column lapzone, it is safe

    • @FactualCivilEngineering
      @FactualCivilEngineering  Před 5 lety +2

      Yea it is safe we can say, but shouldn't be at joint face in any case as per is code

  • @aakashgoyal3899
    @aakashgoyal3899 Před 4 lety

    Sir aap jo Is code use kiya hai wo 2003 ka hai aur iska latest revision 2016 ks hai aapne is video m clearly nhi btaya hai ki beam bottom m kha pr aur top m kha pr lal dena chaiye so plz sir mera req hai ki aap video dobara banaye jisse muje bhot help miligi. Aur sir reply jarur dijiyega.

  • @divyanshityagi9991
    @divyanshityagi9991 Před 4 lety

    At the end you said the spacing should be min 150 mm however acc to IS code it should be max 150mm

  • @atuljha9813
    @atuljha9813 Před 5 lety

    Sir please tell me about lap zone in cantilever beam

  • @utkarshsingh6591
    @utkarshsingh6591 Před 5 lety

    Can you make a video on Productivity of manpower engaged in various tasks on site ?

  • @avinashshrivastav6925
    @avinashshrivastav6925 Před 3 lety

    Sir ham 2d bina chode nhi kar sakty hai lapping.
    Near by column m?

    • @FactualCivilEngineering
      @FactualCivilEngineering  Před 3 lety +1

      Kar sakte h, lekin stirupps / ring ka spacing 75mm c/c rakhna over all lap length par

    • @avinashshrivastav6925
      @avinashshrivastav6925 Před 3 lety

      @@FactualCivilEngineering thank for your reply sir.
      Sir lapping zone of slab p v video banao plzz

  • @haidaralikhorejia8984
    @haidaralikhorejia8984 Před 3 lety

    Ye 1.3time kya hai sir

  • @aakashgoyal3899
    @aakashgoyal3899 Před 4 lety

    Sir beam top main lap center main aur beam bottom m side lap kyo dete hai aur yah bhi bataye ki Beam m top main s.f. aur b.m.kha aata hai aur bottom m kha aata hai aur as per is code. Aur 13920 ka 2016 revision hai aur aap 2003 ke according bta rhe h

  • @shivamkumargupta9379
    @shivamkumargupta9379 Před 10 měsíci

    less than 1.3Times below. What is this plzz explain

  • @suvashpokhrel2351
    @suvashpokhrel2351 Před 4 lety

    If the 2d length fall beyond L/4 then what to do sir? I mean if 2 times of our beam depth is 40 inch and L/4 distance is less than 40 inch which one should we follow?

  • @aakashgoyal3899
    @aakashgoyal3899 Před 3 lety

    Sir top m jo lap dena hai uske bare m aapane details m nhi bataya h

  • @venkatsatyam1878
    @venkatsatyam1878 Před 2 lety

    Amit ur friend

  • @sambathkumar003
    @sambathkumar003 Před 2 lety

    Dear friends can any one tell in the video 8:48 clause 4.4.1 which IS code..please reply me

  • @amitkumarsah9435
    @amitkumarsah9435 Před 4 lety

    U r taking 50% of moment at half of 2nd L/4 .how that?does -ve BM starts at exactly L/4 from the column face?

  • @anandasiridisai
    @anandasiridisai Před 4 lety

    Sir namaskar appka cellphone kya hai , share with me

  • @erajayyadav5888
    @erajayyadav5888 Před 3 lety

    Sir 300mm ho tho

  • @ratankumaryadav7940
    @ratankumaryadav7940 Před 4 lety

    Drawing ke bare janna hai ditel se mughe nhiata hai

  • @rahultechnocad6972
    @rahultechnocad6972 Před 4 lety

    Column में Bottom area में L की length कितनी होती है और क्यों????
    Example
    Bottom mash dai 12mm both side
    Clear cover 50mm
    Footing depth 600mm
    Column bar 16mm
    Ld = 50d = 800mm
    So
    L = 800-(600-50)-24=226mm
    पर ये तो कम है।।।।
    और अगर आप 300mm कहना चाहते है तो क्यों???
    हर जगह जवाब ढूंढा, नहीं मिला, पर आपसे उमीद है।।।

  • @aakashgoyal3899
    @aakashgoyal3899 Před 3 lety

    shear force and bending moment ke Aadhar per Aadhar per Diya Jata Hai Kisi Ek Aadhar per Kiya jata hai aapane pura spasht tarike se nahin bataya hai

  • @aakashgoyal3899
    @aakashgoyal3899 Před 3 lety

    अपने बीम के टॉप बार के लेप के बारे में इसमें डिटेल में नहीं बताया है

  • @aakashgoyal3899
    @aakashgoyal3899 Před 3 lety

    Sar aap ka email id hi dijiye kam se kam apps per reply to kar denge

  • @bhaveshvinzava4794
    @bhaveshvinzava4794 Před 4 lety +1

    Effective depth clear nhi samjaya bro

    • @FactualCivilEngineering
      @FactualCivilEngineering  Před 4 lety

      From bottom of beam to centre of main bar, If Cover 25mm & Main bar 20mm than 25mm + 10mm = 35mm effective cover, also if beam depth 600mm than effective depth of beam = 600mm - 35mm = 565mm, Clear

    • @bhaveshvinzava4794
      @bhaveshvinzava4794 Před 4 lety

      From bottom ki from top sir

  • @Amenshekh6825
    @Amenshekh6825 Před 4 lety

    Sir clause 4.4.1 jo l/4 ka explanation diya he vo samaj me nhi aaya thik se

  • @dulhapur
    @dulhapur Před 3 lety

    Clear Height between plinth beam top and roof beam bottom-11 feets
    Zone-A-11/4=33 inches
    Zone-B-11*12-66=132 -66=66 inches
    There are 6 bars 16mm@4,12mm@2
    At zone B top- 2 no of lappings
    At zone B middle(30 inch below top lapping points)-3 no of lapping
    At Zone B bottom (30 inch below middle lap point)-1 lapping
    Whether the above arrangement is allowble?
    Whether lintel tie beam can be provided any zone?
    What if lintel tie beam falls on zone-A top area?