Duplex ADU Build San Diego, CA - #2 ADU Foundation - Slab on Grade

Sdílet
Vložit
  • čas přidán 13. 04. 2023
  • This channel is designed to help homeowners understand what goes into building an ADU. We are located in San Diego California. For this next project I will be documenting each phase of construction.
    www.urbnbldrs.com
    www.thisnewadu.com

Komentáře • 5

  • @erikgonzalez9941
    @erikgonzalez9941 Před rokem +1

    Nice work! Thanks for these, keep the videos coming for this property

    • @URBNBLDRS
      @URBNBLDRS  Před rokem

      Thank you Erik. Glad you like them!

  • @heyyo2696
    @heyyo2696 Před rokem

    Can i use 1/2 rebar or 1/2 inch copper for the electrical ground?? Did you connect the
    main sewer line 4 inch to the existing sewer line prior to the inspection?? good work.

    • @URBNBLDRS
      @URBNBLDRS  Před rokem +1

      20’ of 4AWG copper wire or 20’ of 1/2” rebar at the bottom of the footing. The sewer connection will be made later. You just need the under slab plumbing inspected.

    • @heyyo2696
      @heyyo2696 Před rokem

      @@URBNBLDRS Yes sir, copy that, i will do the same to my in coming adu. still waiting for the permit, DSD noted that it us in proceses... youre the man.