Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JUL 2024

Sdílet
Vložit
  • čas přidán 26. 08. 2024
  • Blue line updates from Airport to Hebbal. Recorded Date : 14-JUL-2024
    Phase 2B - Airport to Hebbal
    ***********************************************
    JULY 2024 Updates
    Civil Contractor : PKG2 - NCC LTD - 11.678 KM
    PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
    Piling Works Happening and Pier casting Picking up pace.
    Package 2 :
    Kodigehalli Station :- RHS Pier casting in Progress. LHS Piling completed.
    Jakkur Cross Station :- CC Beam casting to begin
    Jakkur Plantation Station : Unsure
    Yelahanka / Kogilu Cross Station :- Concourse beam casting in progress
    Bagalur Cross Station : U girder Done. Concourse i-girders done. Platform i-giders in progress
    Package 3 :
    Bettahalasuru Station : Unsure
    Chikkajala Station : Pier casting is in progress
    Doddajala Station : Beam casting for Concourse level has begun
    Stations done by KIAL :
    Airport City Metro Station : Tenders for Civil works to be awarded.
    Airport Terminal Metro Station : Civil works complete. Finishing works pending
    ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B
    ------------------------------
    Track: Joy - Next Route [Audio Library Release]
    Music provided by Audio Library Plus
    Watch: • Joy - Next Route | Fre...
    Free Download / Stream: alplus.io/joy
    ------------------------------

Komentáře • 59

  • @mmpasupati
    @mmpasupati Před měsícem +11

    Karnataka has started planning for second Airport. They should also plan for connecting this airport other wise it would inconvience for people who want to catch connecting flights bw this airport. Problem with our govt is that they dont include public transportation accessibility when they plan to build infrastructure.

  • @sumitnimawat7408
    @sumitnimawat7408 Před měsícem +3

    Please save trees and lakes love from UP

  • @anilpanchaksharaiah3929
    @anilpanchaksharaiah3929 Před měsícem +2

    I follow you regularly, thanks for sharing detailed videos. keep it up.

  • @shreyass5664
    @shreyass5664 Před měsícem +1

    Hi sir kindly make a video about the double decker flyover which is opened recently.It will be nice to see the flyover through your videos 😊👍

  • @pam6124
    @pam6124 Před měsícem

    Great effort Sunil ji! Thanks so much.

  • @shreyass5664
    @shreyass5664 Před měsícem +1

    Eagerly waiting for the day when all people in the city will travel to airport in metro😊👍

    • @mysterious_billionaire
      @mysterious_billionaire Před měsícem

      Another 4 years probably

    • @shreyass5664
      @shreyass5664 Před měsícem +1

      @@mysterious_billionaire 2026 is the deadline may be max by 2027 they will open .In 2025 I am hoping silk board to kr puram line might open I see good progress in that line.Let us hope all the infrastucture projects complete asap and help the city to get out of this traffic issue and bring back the glory of BLR ❤️😊

    • @mysterious_billionaire
      @mysterious_billionaire Před měsícem

      @@shreyass5664 Ya but the part where KIA has to construct has not even begun yet

    • @shreyass5664
      @shreyass5664 Před měsícem +1

      @@mysterious_billionaire yes let hope they start the work early.👍 By this year end we should see that green line extension and yellow line metro opens to public then it will benefit many people also next year pink will open then around 125kms of metro track will be operational

  • @rajeshreddy842
    @rajeshreddy842 Před měsícem +2

    Very good progress

  • @AbHi-tm5dh
    @AbHi-tm5dh Před měsícem +2

    Good progress

  • @phantompheonixrandome8971
    @phantompheonixrandome8971 Před měsícem +2

    it will finish when my grandchildren are born

    • @SunilHP
      @SunilHP  Před měsícem +9

      This is the fastest it has ever been. I dont know what you are expecting. But civil works take time. by any metro standards this is good pace, thanks to pre cast elements used.

    • @kvgirish100
      @kvgirish100 Před měsícem +1

      This is the fastest metro construction line in Bangalore 😅 but u r saying like this...

    • @vikass8039
      @vikass8039 Před měsícem +8

      ​@@SunilHPಬಹುಷಃ ಅವರ ಸೊಸೆನೋ ,ಮಗಳೋ ಗರ್ಭಿಣಿ 🤰 ಇರಬೇಕು ಬಿಡಿ😅

    • @shreyass5664
      @shreyass5664 Před měsícem +1

      Thanks for uploading 😊👍

    • @girijaramarao4252
      @girijaramarao4252 Před měsícem

      X​@@SunilHP he must be one of those pSickular elite who can not close the fly of his pants ...

  • @rohithd5868
    @rohithd5868 Před 23 dny

    Will the new proposed yelahanka suburban railway station integrated to yelahanka/kogilu metro station?

    • @SunilHP
      @SunilHP  Před 22 dny

      @@rohithd5868 nope. There is none envisaged since the distance is quite much n road is already narrow for a foot over bridge. Yelahanka suburban though will be junction for both airport line n heelalige-rajanukunte line

  • @vijaysrini27
    @vijaysrini27 Před měsícem

    What will the people in Hunesmaranahalli, Vidyanagar and Bettahalasur do to access the metro network? Will Embassy Group/BMTC or BMRCL arrange for feeder bus service for this purpose?
    Moreover, Bengaluru city is likely to expand to around 1000 sq km in future, even officially.

    • @SunilHP
      @SunilHP  Před měsícem

      Bettahalasuru one should ideally have been done. Anyways Embassy seemed to have backed out after multiple follow ups.

  • @prasadanand1252
    @prasadanand1252 Před měsícem +1

    Any updates on yellow and pink line?
    Can we expect tunneling to be completed by October end and the entire pink line atleast by August 2025?
    Will the yellow line be further delayed?

    • @SunilHP
      @SunilHP  Před měsícem +1

      October end for pink line does not look so since they are having issues with tunneling in the final stretch. Having said that BEML trains will have to be delivered for pink line to start. so there is some time left for the stations and tunnels to finish. Yellow line is under testing. Once more trains join in next month from Titagarh , then full fledged testing of signalling can happen.

    • @haneesh__1
      @haneesh__1 Před měsícem

      ​@@SunilHP Is there a good chance for it to open by Jan 2026?

    • @SunilHP
      @SunilHP  Před měsícem

      @@haneesh__1 ORR line can , they started 6 months in advance and are progressing well. All system contracts are in place. If BMRCL goes all out doable.

  • @xxxx-tb4de
    @xxxx-tb4de Před měsícem

    Do we expect this line to get completed by 2027?

  • @gamerartificial7208
    @gamerartificial7208 Před měsícem

    Electric overhead wires like Delhi metro

    • @SunilHP
      @SunilHP  Před měsícem

      @@gamerartificial7208 nope. Bangalore metro all lines including airport one are powered by third rail . So no over head masts anywhere

  • @vijaysrini27
    @vijaysrini27 Před měsícem

    What about Jakkur Plantation, between Jakkur and Yelahanka? Is there any hope, atleast after the metro is complete?

    • @SunilHP
      @SunilHP  Před měsícem

      Even the latest article said the same. But Not sure what is the plan now since most viaduct and piers are built normally. Possibly they may add later.

  • @gamerartificial7208
    @gamerartificial7208 Před měsícem

    14:55 why there are holes in the u gider

    • @SunilHP
      @SunilHP  Před měsícem

      @@gamerartificial7208 earlier this was location of bettahalasuru station. These holes are provided for cabling ( signaling, traction power ) to be routed to station control / near by sub station. Provisioned at cast time to avoid drilling later

  • @mysterious_billionaire
    @mysterious_billionaire Před měsícem

    It will be one big fight when they bring all the lugage into the train 😂😂

    • @SunilHP
      @SunilHP  Před měsícem +2

      In the DPR they have mentioned some luggage racks will be made available. Also they should engage with KIA and have city side check in counters at say Silk board , KR Pura and Hebbal . This will help immensely.

    • @mysterious_billionaire
      @mysterious_billionaire Před měsícem

      @@SunilHP thats nice to hear

  • @vijethkumar6549
    @vijethkumar6549 Před měsícem

    What about On ground line of Airforce?

    • @SunilHP
      @SunilHP  Před měsícem

      @@vijethkumar6549 still to get possession. Both side of IAF Underpass they have piled for cross over pier n service road. High time package 3 gets this. This is the only hold up on their part

  • @shreyass5664
    @shreyass5664 Před měsícem

    In airport line what will be the distance netween 2 station's ?.I heard this line is not like delhi metro airport express line .

    • @SunilHP
      @SunilHP  Před měsícem

      Till Yelahanka its like normal spacing of metro. After that stations are spaced apart to cut down travel time. only Bagalur cross, Chikkajala , Doddajala after that before arriving at Airport city station and ultimately Airport terminal metro station.

    • @shreyass5664
      @shreyass5664 Před měsícem

      Thanks ​@@SunilHP

    • @shreyass5664
      @shreyass5664 Před měsícem

      In the last airport terminal station will the station will be between two terminal connected by Skywalk?

    • @shreyass5664
      @shreyass5664 Před měsícem

      Will the last airport terminal station be placed between both terminals connecting them by Skywalk?or how it will be connected to the terminal entrance

    • @SunilHP
      @SunilHP  Před měsícem

      @@shreyass5664 yes between two terminals and be walkable to T2 atleast . T1 I am not sure.

  • @SathyaswamyS
    @SathyaswamyS Před měsícem +1

    India superpower 2047 sar

  • @p__1-1__d
    @p__1-1__d Před měsícem

    Is the exact location for Airport City station confirmed?

    • @SunilHP
      @SunilHP  Před měsícem

      As per the plan available, it is close to the location on the infographic.

    • @p__1-1__d
      @p__1-1__d Před měsícem

      @@SunilHP Thank you for the reply! I presume it's not possible to know any further based on construction since they have not yet started work on the station itself? Is there anyway to tell based on type of pillar etc.?

    • @SunilHP
      @SunilHP  Před měsícem

      @@p__1-1__d No this would be an grade station , so till they start work we will not know :-) Tenders were called sometime back by KIAL. Not sure whether it was awarded. Let me see if I can check through some sources.

    • @p__1-1__d
      @p__1-1__d Před měsícem

      @@SunilHP Much appreciated :)