Quantity of cement sand and aggregate for 1000sqft slab| Material required for 1000square feet slab
Vložit
- čas přidán 28. 04. 2022
- 1000 स्क्वायर फीट छत की ढलाई में सीमेंट बालू और गिट्टी कितना लगेगा?
In this video, I have explained about how to calculate material quantity for 1000 sq ft concrete slab.
1.54 is a factor that helps us to convert the wet volume of concrete into dry volume.
Requirements Quantity for 1000 sq ft Slab.
1- Cement
2- Coarse Sand (Morang)
3- Coarse Aggregate ( Gittee)
#1000squarefeetslab #concrete #civilengineering
To watch more videos on:
Cement, Sand and Aggregate Calculation for M-25 Grade of Concrete
• Video
How to Calculate Quantity of Cement and Sand in Plaster
• Video
Please do not forget subscribe the channel
Thank you
#RighCivilEngineering
very nice information
Excellent Calculation,
Sirji steel kitna lagega 1000 sq.ft area mey?
Very very valuable information
तुम भी गधे और ये भी गधा।
Good knowledge very useful
Thank you
Good work bhai
Very very good
smit aur bajri kitni couontity me mix karte hain thori si banani ho to.simt zyada ya bajri zyada letay hain ?
Nice 👌
Nice video
Volume of cement= 116.2 cft
(Volume of cement per bag = 1.23 cft )
.....
116.2÷1.23= 94.47 (95 bags)
.........
.........
@shortcut
6
Sir 500sqft mumty ki slab casting karni h kitna hm material mnga le
suresh oraon sir bim aur colam ka cement agreegate 15:08 sand sarya ka volume nikalna sekhai kitna kitna lagega
Oky jld hi video ek aap ko mile es topic pr
Bhai 1200 square. Kit na. Steel. Lage. And send. Aggregate and Chement bag please reply
😮
Sir 14 brash me ret kitna tan chahiye btaye sir
Hii sir. Iss calculation me wall beam add he ya sirf slab ki calculation he
Sirf slab h
Good
Thanks
Ultra tech cemente Dalai me Kitna Bali auro goti aur pani dena he
50 kg me
Sand. 0.3 cubic feet
Aggregate Or Gitti- 0.6 cubic feet
Bhaee
3000 sq ft k roof casting may gittee ,baaloo lagaiga
1044 cubic foot.
Manojkumar ❤❤
1000sqft ki slab usme kharcha kitna aye ga
Sir 1000 sq feet me sand aur aggregate itna kam lgega mere khyal se jayda aayega sand only 183 cft how can possible
Galat 5" in feet 0.41
Sir.hamari.slab.on.thuosend.scear.hai.es.ma.kitne.cement.laga.gi.sAlabthiknes.6.inches.hai
Video me procedure btaya h maine
Ab shop wale se cft m material mngal pedega
Cft. Jo hai material ki measurement unit hai
Cement Bag me ata hai
Coarse sand - cube foot (cft.)
Aggregate (Gitti) - cube foot (cft.)
Steel MT or Kg. or Kuntal
Sir,kitna tractor sand aur kitna tractor aggregate hoga.pl bataiyen.
Slab area kitna hai
But the shrinkage factor is variable segment how could it takes 1.54 at every zones or in every locations in a period of variable weather??
1.54 is a factor with the help of which we convert wet volume to dry volume.
I've used Shrinkage Factor world here to say that when we mix cement, sand and water, the dry state, our volume remains, it shrinks a bit. Means reduction is dry volume, that's why I have used this word. here.
I have explained this word in the description also so that people should not get confused.
@@rightcivilengineering 0p
Balu aur gitti ki matra braber hai to usase koi nuksan hoga kya
1250sq fit me kitna kiya sb lagega
Cement -114 bag. , Coarse sand- 209cubic foot. Or Aggregate (gittee)-416cubic foot.
Cft means kya hai 😔
Bro aggregate kitna ft lagega.... Ft mei bataye Thora reply please
Cubic Feet
1000 sq ft slan main kitney Horitental and Longitudnal beam dena hoga and kitna beam to beam difference ragna hoga .
Jaha jaha walls a Rahi hai room me waha de deejiye beam
Sir shed hai 175x35 feet .sir there is no wall below the shed howevr column given at distance 15 ft. Please advice how should I proceed.thnx
Sariya ka area minus nahi hota?
Nahi
Bhai sariya kitne quantal laga hai
1.8 kuntal
How to calculate the quantity of iron?
4 kg of steel is required per square foot of built-up area in slab
@@rightcivilengineering उच्च ढं
Plz stèeĺ also for 1000
Only civil or architect understand
Sir main ek mistri hoon
Lekin same ka formula Maine khud banaya tha
Very good
Is video main aap ko slab beam add karna chahiye tab ja k ye video complete hota . Abhi ye video incomplete hai . Bina beam k slab yahi chat nahi dhala jata
Oky next video me aap ko complete mile ga
1700 sqf mey cement kitna beg hona chahiye
120
Steel bar kahaan Gaya brother
Ek complete video ane wale jisme steel ko bhi add Kiya h
Cft ko fit me bataye
Oky
Bhai aggregate (gitti) aur baalu cft me hi aata hai hum log use feet bolte hai Jo kihamari galati hai...
Iron rodes reh gai. Rest all ok
Steel kaha gaya sir
Steel ke bare me es video me nahi btaya ho
Galat.volume nikale sirf slab ka .beam nahi hai kya slab me.
छोटी सी बात को इतना लंबा कर दी है कि समझने वाला पागल हो जाएगा
🙂
vo tumhe abhi choti si baat lag rahi hogi jab pehla din hota hai to shrubaat ese hi karni padti hai. thnku
Steel gayab
4 kg of steel is required per square foot of built-up area
Band ful raha hay a video
861 me
Cement -78 bag. , Coarse sand- 144cubic foot. Or Aggregate (gittee)-279cubic foot.
इसमें आपने छत की ऊंचाई नही बताई है उसको भी बताओ
1 bag of cement = 1.25cft .kahe wt k chakkar me jaa rahe hai.
Ratio of material is..1:1.5 : 3
100bag cement
150 bag sand
300 bag aggregate
About 1000 kg steel.
छत की ऊंचाई कितनी है
it. is. very. sad. to. say. your. hand. so. shabi.it.self.proof.of.bad.to.wors.acknowledge
Bhai maths bta rahe ho
Aap uljhaate bahut 😢ho sir chhoti see baaat ko itta bda kyon bna diya
Next video Ane wala hai usme short me btaunga . steel ke saath
BHAI WRITING THEEK KR. 😁
अबे कहाँ से रट्टा मारके आया है 6:39 पर सारी बात खत्म हो गई आगे क्यूबिक मीटर में कन्वर्ट करने की क्या जरूरत है जो भी answer आया है उसे 1.25 से डिवाइड कर दे सीमेंट के बैग की क्वांटिटी आ जायेगी।
Good
Thank you
Nice video
Thank you
1800sq ft me kitna material lagega