EG4 Power Pro 28.6kWh + Luxpower 12k (EG4 18K). Home battery backup installation.

Sdílet
Vložit
  • čas přidán 28. 07. 2024
  • Installing 2pcs EG4 PowerPro and Luxpower 12k inverter (also known as EG4 18k).
  • Věda a technologie

Komentáře • 59

  • @benkanobe7500
    @benkanobe7500 Před 4 měsíci +2

    You have come a long way from Blue China GTILs! I'm still there but am looking at the LUXpower 6K as they have current clamps and I don't want a contract with my utility. I have two Blue Boxes for day time and two for night time (batteries) I finally learned how to use the battery function and it makes so much sense! Set amount in watts you want to limit the battery bank to output, and use internal limiter to control each Leg up to the set limit. It works flawlessly. I use a regular AC battery charger during the day to recharge the batteries as the panels are keeping the house loads from grid at just a few watts. So no charge controller for batteries, just the AC battery charger. The system works perfectly thanks to all your CZcamss from back in the day of your blue box GTIls!

  • @zwei176
    @zwei176 Před 3 měsíci +3

    Love these videos. Great prep for my 18kpv and PowerPro install soon

  • @benkanobe7500
    @benkanobe7500 Před 4 měsíci +2

    You do First Class Work!

  • @1982757
    @1982757 Před 4 měsíci +7

    Why expose the batteries and inverter to direct sunlight? Although they may be rated for outdoor use, electronics still suffer from increased temperature and you may want to advise them to get a shade over the installation.

  • @carlosschmidt6035
    @carlosschmidt6035 Před 3 měsíci +1

    Nice and Clean Job !!

  • @ram64man
    @ram64man Před 27 dny

    Beautiful work , so neat

  • @AveRage_Joe
    @AveRage_Joe Před 4 měsíci +1

    Great Work Man!!

  • @Electronzap
    @Electronzap Před 4 měsíci +1

    Looks good!

  • @andys5203
    @andys5203 Před 23 hodinami

    Awsome video. Can you tell me if the RSD is used does it kill power to the subpanel circuit? Thks

  • @DJLsbVapes
    @DJLsbVapes Před 3 měsíci

    Great job, question, do you need to be certified and licensed to install these systems?

    • @SolarEngineering
      @SolarEngineering  Před 3 měsíci

      usually if batteries involved, city want to see electrical license

  • @jimmybrad156
    @jimmybrad156 Před měsícem

    No ferrules for bare wires?

  • @punksjutgbd
    @punksjutgbd Před 4 měsíci

    Love your installs.
    Does this have an automatic transfer switch built-in?
    What did you charge for this install?

    • @SolarEngineering
      @SolarEngineering  Před 4 měsíci

      >>Does this have an automatic transfer switch built-in?
      yes 200A pass-trough
      >>What did you charge for this install?
      each installation is unique and price vary

  • @jeffreylee5714
    @jeffreylee5714 Před 3 měsíci

    Great install as usual. Would you be able to share some of the permitting drawings used for your installs like this one? Redact/Blackout personal information. Thanks

  • @USA-GreedyMenOfNoIntegrity
    @USA-GreedyMenOfNoIntegrity Před 4 měsíci

    Good luck with any customer service after the sale needs.

  • @danieldorchester5221
    @danieldorchester5221 Před 14 hodinami

    If you put the batteries closer together would the battery cables have reached?
    I’m doing the same install next month.

  • @Pete856
    @Pete856 Před 4 měsíci

    Why do they need batteries without solar, are they saving money on time of use? If it's for blackout protection, then they should just keep the generator.

  • @Mac_Raymond
    @Mac_Raymond Před měsícem

    Wish you serviced the modesto area. I'm looking to have the 18k, 2 batteries and some solar installed.

  • @diggerbrass
    @diggerbrass Před 4 měsíci

    For paralleling 2 PowerPro batteries, doesn't EG4 suggest connecting the second battery to the bus bar of the first battery? And then from there, running two battery cables up to the inverter from the bus bar?

  • @andrewdunham8973
    @andrewdunham8973 Před 4 měsíci

    Out of curiosity, what kind of wire did you use when making a new negative cable?

  • @paulbram2
    @paulbram2 Před 5 dny

    could you technically power the entire home using backfeed to the main panel? I'm interested in a similar setup, but don't want to have to pick/choose my critical loads and would rather do a whole home backup up to the max 12K the inverter can support. I think the system will auto pull from the grid for any loads over 12k?

    • @SolarEngineering
      @SolarEngineering  Před 4 dny

      you'll need to relocated all loads from main panel. Or install tesla backup switch, which can do full-home backup without circuits relocation.

  • @pederb82
    @pederb82 Před 4 měsíci

    How did you end up making it watertight between inverter and battery. It looked like some of your holes only aligned and the rest was left open? Is there maybe a seal between the two units?

    • @SolarEngineering
      @SolarEngineering  Před 4 měsíci +1

      a small line of construction adhesive on the perimeter.

    • @pederb82
      @pederb82 Před 4 měsíci

      @@SolarEngineering thank you for answering me. :)

  • @seanj2011
    @seanj2011 Před měsícem

    Can I ask why you used what looks like AWG 4 or 6 for the grid/load?

    • @SolarEngineering
      @SolarEngineering  Před měsícem

      it's a partial backup. Inverter replaced 50A generator. So I'm using 6AWG

  • @curacao11
    @curacao11 Před 4 měsíci +1

    😎

  • @PaulPushkarov
    @PaulPushkarov Před 3 měsíci

    I am curious - why LuxPower and not EG4 18KPV? Seems like they cost the same but you get two parts from the same brand that supposedly should work better (more reliable?) together.

    • @PaulPushkarov
      @PaulPushkarov Před 3 měsíci

      Oh I watched the video again and you did mention that they are the same inverter.

    • @SolarEngineering
      @SolarEngineering  Před 3 měsíci

      yeah, EG4 18K is a white-labeled version of LuxPower 12k.

    • @joeshmo551
      @joeshmo551 Před 7 dny

      @@SolarEngineering yes but with separate support staff and software/firmware correct? Has there been any call backs? Luxpower is a spin of from a China inverter company "Ningbo Deye Inverter Technology"

  • @Adrayven
    @Adrayven Před 3 měsíci

    What knockout tool is that you’re using? Like to where to buy?

    • @SolarEngineering
      @SolarEngineering  Před 3 měsíci

      Milwaukee 49-16-2694 M18 Exact 1/2" to 2" Hand Ratchet Knockout Set
      amzn.to/3J1C9Mm

  • @tvguide4khv
    @tvguide4khv Před 3 měsíci

    use blackmagic DaVinci Resolve 19 editor to isolate voice from bg noise and boost it

  • @nickpatel5419
    @nickpatel5419 Před 4 měsíci

    Is this setup UL9540 listed? Did the AHJ approve it?

    • @SolarEngineering
      @SolarEngineering  Před 4 měsíci +1

      yes and yes

    • @nickpatel5419
      @nickpatel5419 Před 4 měsíci

      @@SolarEngineering Can you link to the certification? I'm not finding it online.

    • @SolarEngineering
      @SolarEngineering  Před 4 měsíci +2

      @@nickpatel5419 eg4electronics.com/backend/wp-content/uploads/2023/11/UL9540-PP-WallMount-AW18kPV-ESS-Certificate-of-Compliance.pdf

    • @nickpatel5419
      @nickpatel5419 Před 4 měsíci

      @@SolarEngineering Thank you! Technically this is not a 9540 supported configuration.
      eg4electronics.com/backend/wp-content/uploads/2023/11/ESS-9540-Detailed-Configuration-Requirements-1.1.pdf
      I guess if the AHJ approved its ok??

    • @nickpatel5419
      @nickpatel5419 Před 4 měsíci

      @@SolarEngineering Thank you. Technically, this is not an EG4 UL9540 configuration.
      eg4electronics.com/backend/wp-content/uploads/2023/11/ESS-9540-Detailed-Configuration-Requirements-1.1.pdf
      But if the AHJ approves, I guess it's good??

  • @3er328
    @3er328 Před 3 měsíci

    What area are you located ?

  • @PosiP
    @PosiP Před 3 měsíci

    Would not pass inspection. Low Voltage and High Voltage can't be pulled in the same hole.

  • @user-ol2sm9jq9g
    @user-ol2sm9jq9g Před 3 měsíci +1

    That LCD is going to fail. There should be some sort of a cover for the display. Sometimes you can buy a magnetic screen cover for it to block the UV rays.

  • @kickgas7171
    @kickgas7171 Před 3 měsíci

    I would never use a low surge, high frequency, transformerless inveryer to power my home. They offer poorer peak power capacities and a shorter life expectancies than heavy duty, low frequency, transformer based inverters.

    • @SolarEngineering
      @SolarEngineering  Před 3 měsíci +1

      what is the alternative?

    • @kickgas7171
      @kickgas7171 Před 3 měsíci +1

      @@SolarEngineering The alternative is a heavy duty, low frequency, transformer based inverter charger from manufacturers like Magnum Energy, Schneider Electric, Sigineer Power, Outback Power or Victron Energy.