Example 1 Earned Value Management Made Easy
Vložit
- čas přidán 20. 05. 2019
- Example 2 - EVM made easy (CZcams Link: • Example 2 Earned Value... )
Example 3 - EVM at Task Level to Project Level (CZcams: • Example 3 - EVM at Tas... )
Microsoft Project; Earned Value Analysis - Example 1 ( • MS Project - Earned Va... )
/ @pieterrademeyer1 (Visit my Channel for Project Management topics and videos)
An earned value management analysis example is discussed in this video explaining the following: planned value(PV), actual cost (AC), earned value (EV), and budget at completion (BAC). The following are also explained and calculated: schedule variance (SV), schedule performance index (SPI), schedule variance percentage (SV%), cost variance (CV), cost performance index(CPI), cost variance percentage (CV%), estimate at completion (EAC), estimate to complete (ETC), variance at completion (VAC), and the to complete performance index (TCPI). The formulas for earned value management can also be obtained from the Project Management Body of Knowledge (PMBOK).
Pieter, you are a gifted person. The way you explained is so easy to understand.
The best EVM presentation ive seen in a while
Really clear explanation and understandable presention. Thank you very much!
I agree with the other comments, this is the clearest and easiest to follow presentation of Earned Value! Thank you so much for creating this.
Great presentation, thank you Sir.
This is the best EV presentation I have seen. Very clear. Do you also have one for burn-down charts?
Thank you Pieter ive been looking for a easy explanation like yours... its the best video explaning the Earned Value Management
Great video. Doing PM414 at Stellies for Engineering final year and this explains so well.