MS Project - Earned Value Analysis - Example 1 - Assign Resource to Tasks

Sdílet
Vložit
  • čas přidán 1. 06. 2024
  • Example 3 - EVM at Task Level to Project Level (CZcams: • Example 3 - EVM at Tas... )
    MS Project: View Free, Total and Zero Slack or Float: • MS Project: View Free,...
    19 TIPS for setting-up the perfect project: • 19 Tips for setting-up...
    / @pieterrademeyer1 (Visit my Channel for Project Management topics and videos)
    In this video an example is used to show how to do earned value analysis using Microsoft Project of MS Project. In the example resources are assign to tasks in order to generate the project cost (i.e. baseline cost)
    The following steps are followed:
    Step 1: Assign resources to tasks
    Step 2: Switch off “Actual cost are always calculated by Project”
    Step 3: Set Earned Value options for the project
    - set default task Earned Value method (% completed)
    - set baseline for Earned Value calculations
    Step 4: Set project baseline
    Step 5: Set the project status date
    Step 6: Add project progress (% complete & actual cost) to status date
    Step 7: Earned Value Tables and Report

Komentáře • 3

  • @ZHA2065
    @ZHA2065 Před 2 měsíci +2

    I can't thank you enough ❤

    • @lelompume7403
      @lelompume7403 Před měsícem

      Me either this is the best clarification i have seen so far i must say thank you.

  • @user-yh6fk8tu1v
    @user-yh6fk8tu1v Před měsícem

    Can you pls make a video deffrence of critical path vs critical chain?