Another amazing video. it really gives you a good understanding of earn value calculation on Planned dates vs Current Dates. Thank you so much sir. This video is very educative.
Hi. Thank you for you wonderful videos. I have a question bothering me, the question is; How can I put the right activity relationship in the send of MEP rough-in phase work with structural phase work? I have seen so many videos linking MEP rough-in work after completion of structural which I think shouldn't be. Pls correct me, Engr
Linking activities isn't a straightforward process. As planners, we aren't solely responsible for determining the sequence of work. Typically, we discuss this with the project manager to set the work execution sequence. Additionally, the sequence can change depending on the project type, location access, and material delivery schedules.
Our NEW Progressing Course just launched!
Check out the best Advanced P6 Training available online:
www.planacademy.com/
I'm having this exact situation at 5:00!
Another amazing video. it really gives you a good understanding of earn value calculation on Planned dates vs Current Dates. Thank you so much sir. This video is very educative.
Amazing. Your effort is highly appreciated. Thanks for sharing the concept and for letting us know the tedious points of P6.
I don't know about amazing. But we appreciate your supportive words. Thanks!
Very intuitive. It really made sense to me. Thank you.
Awesome. Glad it helped!
Thank you Michael! Excellent short video!
Glad you liked it!
I really wish that Oracle would add Earned Schedule Management to its program.
Well done. Thank you
Very helpfull, thanks for sharing
Hi. Thank you for you wonderful videos. I have a question bothering me, the question is;
How can I put the right activity relationship in the send of MEP rough-in phase work with structural phase work? I have seen so many videos linking MEP rough-in work after completion of structural which I think shouldn't be. Pls correct me, Engr
Linking activities isn't a straightforward process. As planners, we aren't solely responsible for determining the sequence of work. Typically, we discuss this with the project manager to set the work execution sequence. Additionally, the sequence can change depending on the project type, location access, and material delivery schedules.
It´s not a problem in Version 22
I always use at completion or budgeted values with "current dates". I discovered this the hard way. Planned dates option should not exist!