How to Audit VDA 6.3 (P2) Project Management

Sdílet
Vložit
  • čas přidán 6. 07. 2024
  • In the Short video we will demonstrate what VDA 6.3 P2 questions to ask; to determine if a project will be successful.
    Key Question are:
    1) Do you have a Project Management Process documented?
    2) Do you have a qualified Project Manager and Project team? Did you identify the resources needed to ensure that the project milestone will be achieved?
    3) Are all suppliers involved in the project planning phases?
    4) Do you have a project Plan which include the critical path to ensure the customer milestones will be achieved?
    5) Do you have the quality planning activities included in your Project plan?
    6) Is change management within the project ensured by the project organisation?
    7) Do you have an escalation process to inform the management and the customer if there will be delays.
  • Auta a dopravní prostředky

Komentáře • 7

  • @KacemAmineJa
    @KacemAmineJa Před 5 lety +1

    Thank you , your videos are so vailable for me

  • @sankim7007
    @sankim7007 Před 4 lety +1

    that's great video to know how VDA6.3 is working. To me, it's very as similar as IATF16949.

  • @wiliamsherbie
    @wiliamsherbie Před 2 lety

    Would a process flow come in between the DFMEA and the PFMEA?

  • @vikaskumarsingh26
    @vikaskumarsingh26 Před 4 lety

    First I would like to tell you thanks for P2 vda6.3 and are requesting to you please share P3 video like that.

    • @QualityComSolutions
      @QualityComSolutions  Před 4 lety +1

      Thank you. We are in the process to finalize the P2 video. Should be released on the 11 October.

    • @dipanshusaraswat6728
      @dipanshusaraswat6728 Před 4 lety

      @@QualityComSolutions Sir can you please share micro level project timing plan as per VDA 6.3.

  • @pso4ctb219
    @pso4ctb219 Před 2 lety

    Could you please send me the P2 and P3 Turtle?