Critical Path Method with Dummy Activity | CPM Network | Critical Path | Total Floats & Free Floats
Vložit
- čas přidán 10. 08. 2020
- Here is the video about CPM (Critical Path Method with Dummy activity)
In that we have seen how to construct CPM network, how to determine the critical path and project completion time, calculation of Total float and Free float.
Please try to watch complete video to get the clarity about this topic.
==-Don't forget to Like, share and subscribe-==
To Download PDF: drive.google.com/file/d/1jaau...
►Playlist CPM PERT CRASHING : • CPM - Critical Path Me...
►Playlist Operations research collections: • Playlist [Operation Re...
Follow Us On:
===============================
►Instagram: / kauserwise_offical
►Main Channel: / @kauserwise
►KauserwiseQT: / @kauserwiseqt
►Kauserwiseaccounts: / @kauserwiseaccounting
►Kauserwise Tamil: / @kauserwisetamil
===============================
👇List of Subjects and it's Play List👇
►Financial Management
►Financial Accounting
►Corporate Accounting
►Cost and Management Accounting
►Operations Research
►Statistics
Link for ►Playlist - FM [Financial Management video collections] • Playlist FM Financial ...
Link for ►Playlist [Financial accounting tutorial collections] • Playlist [Financial ac...
Link for ►Playlist [Corporate accounting tutorial collections] • Playlist [Corporate ac...
Link for ►Playlist [Cost and Management accounting collections] • Playlist [Cost and Man...
Link for ►Playlist [Operation Research video collections] • Playlist [Operation Re...
Link for ►Playlist Statistics video collections • Playlist Statistics vi...
Thanks
kauserwise®
I cant thank you more ma'am, only with your help I passed quantitative techniques in my MBA. Thank you so much.
No words to say about your lecture mam, you're my role model because in my early high school days I had one maths mam and higher secondary level another one mam and my UG and PG Two mam and one Sir But Now you are also my Best(GURU in Tamil) Teacher. Now I'm also Professor I'll teach your OR video to my students.Thankyou so much madam......
Hi madam, the way you are explaining the things are very clear in this video. I am doing CMA Final. This video helps me a lot to know the CPM Network. Thank you for the amazing video.
Since 11th standard I'm learning from you now I'm pursuing CA and bcom. Grateful :)
I bow to you on how simple you made these lectures to me
This video is helpful even in 2021 with supperb explanation ....
What makes the video perfect is before solving any problem using any formula at first you are explaining the formula definition then formula and next usage which makes to remember the flow of the problem and the concepts too ...
And with your simple english and detailed explanation adds more value to the video ...
THANKS FOR THE VIDEO ...
LOTS OF LOVE AND CARE FROM HYDERABAD ...
Mam, the way you teach, leave no room for doubts. Thank you very much.
மிக அழகாக புரியும்படியாக இருந்தது. நான் படித்தது தமிழ் மீடியம் ஆனாலும் நன்றாக புரிகிறது உங்கள் பணி தொடர வாழ்த்துக்கள்.
நன்றி
@@kauserwise neenga tamizha
Mam! Thank you! You helped me in clearing all my doubts within an hour. You're one of perfect lecturer
You're actually the best in lecturing 👏 I just love your lecture ❤️. Thank you
Thank you so much ma'am for all these lectures, they are life savers for us students, specially in this lockdown. Thank you!
Thank you so much to your channel🙏🙏🙏Your are helping students a lot in learning this subject. I'm really feeling thankful to you & your videos. That has helped me a lot in getting good Mark's in my semester result. I really felt so doubtfull before watching your videos because in my college they didn't explained this shortcut methods. After watching your videos I got confidence to write my exam & got good grade in that. Thank you so much🙏🙏🙏 I definitely suggest each & every student to use this platform👏👏
Soothing handwriting and nice presentation mam. I'm so happy that I saw this channel. THANKYOU SO MUCH..
Nice explanation ma'am I was confusing with these topics but after listening to your lecture it's completely Clear for me THANKS YOU ma'am 🙏❤️
am thanking to kauser wise i was civil engineer and i started Master of cpm so i visited these lessons last months and it helped me more. thank you kauser. you really amazing, educated and professional. i would like to be your student. greeting you from Somalia.
Thank you for your comment, All the best....
Thank you mam your classes have been a great relief during lockdown
I love your lecturing method mam , I enjoy your videos continue great work. Currently am doing project planning , ,,, wow am enjoying your lectures
Your teaching style is great. Thank you
Absolutely very good teaching madam. So steady and clear it is. Excellent madam👍.
Thank you.
You explained everything very deeply also your method of teaching is awesome, You cleared all the points related to the topic, thank you so much for this effort!
Thank you
Thank you madam, your lectures helped me to clear exam in short inverval of time
I am from jammu kashmir and prepare for competitive exam this is very helpful THANKS MAM
Thank you so much for all of these videos, you literally saved me. I couldn't understand a thing before watching your videos and now I'm good :)
Amazing teaching with easiest and clear method
You have explained this so beautifully thank you.
mam aapne bohot easy way se samjha diya .....thank you
In this lecture you showed dummy activity pointing from node three to node two..but as per I know arrow should always show smaller node number to greater one. Can you please elaborate on this?
Thank you so much mum😭🙏♥️♥️God bless you.
Very clear explanation and presentation , was long but worth it
Excellent madam to teach in clear manner
thank you so much for your teaching with clear explanation
Thank you so much ma'am your explanation was very helpful for me ...
According to my professor, we don't consider dummy activity in calculation, whom to believe or there is something to know about somewhere I will consider it somewhere not?
I had completed my MBA and I thank you for helping me out in financial and cost accounting topics.
Its been 3 years and suddenly your video of journal entries clicked in my mind(i dont know how) but i went searching you on CZcams but i was not able to recollect your channel name.
so there was a video having thumbnail similar to what i was searching and i got that but to my utter surprise it was your video but there was only one of it..
But luckily I got your channels name from there only.
I am happy now.
Thank you from the bottom of my heart as your video had helped me and my batch mates immensely.
Keep teaching Madam
Thanks once again!!
**and name of that fake channel is "amjed anver" he has uploaded your teaching video and got 66k views on the same.**
Nice teacher, impressive method, conceptual clarity
Thanks a lot ma'am ... Your lecture help me a lot
Good explanation madam ...i had clear all my doubts about draw a network diagram
Pls do schedule 3 final accounts, your lectures are very helpful
maam for dummy activity fulkerson's rule is not followed ,so do we have to change the 2 and 3 nodes??.. please clarify anyone
Heartfully thank you so much mam❤️..really great lecturing skills mam..I hope be happy if where you are🥺
Thank you so much mam clear explanation easy to understand🙂👍
Thanku very much mam clear explanation 🎉🎉
Should we go for dummy line while calculating ESJ if the B is greater than A
Your videos helps alot......
Thank you sooooo much..
Does it matter that the dummy activity was from node 3 to 2 and not the other direction? Node 2 to 3? Does this change any of the given calculations?
madam you showed a dummy activity pointing from node three to node two..and also node 6 was pointing to node 7,other sources state that an arrow should always show a smaller node number pointing to a greater one. Can you please elaborate on this?if any 1 can explain this to me i will really appreciate it
Maam .. please reply .. does way of solving lpp using big m method and simplex method are same ?
Dear ma'am if suppose A has duration 2 then earliest starting time on node 2 will be 3.that's right or not??
Ma'am but in last cpm method when you calculated total float you calculated as upper box that is earliest starting node and upper box of latest ending activity and than why is it here in this method lower box of earlier starting activity and lower box of earlier starting activity and then minus duration please give me a reply my exams are there i am confused
Thank you mam kindly explain about inventory models with problem that will be more helpful
Why node B consider for EST ??
For activity -3 (through dummy activity )
EST- EST NODE 2+ dummy ??
Please tell
Thank you very much,
Thanks you so much from the bottom of my heart mom ❤❤
Thanks I understand well
Sir thank you it's good teach
too helpful, thnkew mam
Hello mam I wanted to ask if it is possible the dummy arrow go from activity A to B????
HAPPY TEACHER'S DAY ma'am
THANK YOU SO MUCH ma'am FOR ALL YOUR BLESSINGS.
🙏🏻🙏🏻🙏🏻🤗🙏🏻🙏🏻🙏🏻
Thank you Dear
This same question was asked by university in last year,, thank you
Which university
My only hope your lectures mam♥️when I don't get operation research at all.
Thank you mam this vdo helps me a lot🙏🙏
very well explained madam. Thanks a lot
Very useful and informative mam
But activity C & D have same starting and ending nodes? Can someone please explain?
Thanks very much ma'am
Please it will be of help as well
If u teach about Time series Analysis and Price Index number
Thanks so much for ur help so far
Thanks alot Kauserwise....
Thank you mam for this great video
Mam here dummy arrow is going on backward side which is not allowed.
3 to 2 is not allowed na. And backward is also
God bless you Ma'am....
Mam do videos on these topics
1) Account current
2) Average due to date calculation
3)Sale of goods on approval or return basis
4)Bill of exchange endorsement and other various conditions
maam can dummy activity appear on the critical path of of the project network?
Hello Ma'am.
I have an assignment about proposing a network plan and critical path. Can you please explain how I can do that?
Thank you 🌟💯
Wonderful explain for useful mam tq 👍
thnq so much mam
may you be happy always❤
Thank you
I don't know what to say but thanks for explaining in such a beautiful manner!!
Aditya can u clear my doubt which is
In connection network why there is joining of J and I activity which is the last node 8
I CPM problem o would you to help me out with please.I can't draw the network..
Very professional !!!!!
Mam shall we include dummy activity in critical path??(not in this problem).In other problems.
Mam can u put a video for comparative balance sheet..common size balance sheet...common size income statement in management accounting........and job sheet,batch costing,contract costing in costing......your all videos are superb mam...very usefull for me..thankyou mam
Awesome Teachings
Hello madam can you please upload a video of inventory model , simulation , waiting model , probability for mba students . Your videos are very useful for us .
Why don't we draw dummy activity from 2 to 3 rather than 3 to 2 .? Can we draw like that?
Mam how a,b ended in different node bcz they are dependent and together and end in same node?
Hi mam pls teach us leverage chapter & also resource levelling in CPM . It will be very useful for all .
great you are the assets of education sector maam
Thank you...
Hello ma’am! I’ve been following your channel for sometime now & I needed your help in solving OR related problem. Can you please help me? I’ve my exam on 25th of August
Due to lockdown we didn’t have proper classes. Please consider this! Thank You🙏🏻
Hello Mam Please Upload the video about Queing theory
your videos Are Very Much Help Full To me.
You lecture well Ma'am. Please can you upload a video on RANKING OF ACTIVITIES? THANKS
Mam have to you done any video on alternative optimal solution in assigments please share the link as soon as possible
Mam in this video ur take the big or large problem plz update direct problem like activity (1-2).(1-4) and duration in a day
what if there was one more activity which has "A" as a predecessor because now we have no isolated activity 'A" , already combined with another dummy activity .. please reply mam !!!
activity predecessor duration(days)
A - 11
B - 15
C A 5
D AB 10
E B 5
F CD 2
G EF 7
here we have combine AB for activity D , But we need to draw activity 'C" also from 'A' , so where should be 'C' started from, as we dont have an isolated activity 'A' now
Thank you so much mam🌻🎈🎈
i like your blue pencil very cool
outstanding
Thanks for your valuable teaching time for us,i have seen your youtube videos related to OR subject,you thought us with clearing all doubts such a perfection never seen and with such clarity,Thank you once again mam🙏🙏
#Worth watching
Why do u take the path 7_8 could you please explain
Hello ma’am. Hope you’re doing well. Thank you for the classes. They have been been of a great relief. However, can you kindly drop any of your contacts for direct communication? Thank you!🙏🏾
Thank u so much mam
ma'am isnt there two routes for node 7?