Mt Owen 62hr Possession Rail Turnout Installation

Sdílet
Vložit
  • čas přidán 24. 05. 2017
  • Abergeldie’s rail teams have reached a new milestone over the April rail close-down in the Hunter Valley, as our teams worked around the clock to simultaneously deliver work packages at Mount Owen, where a 1:15 swingnose right hand turnout was installed, with a full track recon; and at Scone cutting, where 220 metres of track and formation were removed, reconditioned and replaced.
    The April works followed up on the Abergeldie teams’ achievements at Kooragang during the February 2017 shut down, where re-railing, points replacement and signalling decommissioning were successfully delivered.

Komentáře • 3