  • Our base plumbing system is complete so before we backfill we need to do a 10 ft static water test. Check out the video to see how it went!

Komentáře • 8

  • @jessesilver
    @jessesilver Před 11 měsíci

    Thanks for documenting this! Super helpful for all of us. I know you mentioned wrapping the pipes to account for a bit of concrete expansion but I don't think I see any of the pipes going through a sleeve in the footer, which is something I've seen on other videos (IE any pipe going through the footer goes through a sleeve 2 sizes larger than the pipe size. Not required in your area?

    • @BuildItLikeBeckhams
      @BuildItLikeBeckhams  Před 11 měsíci

      I think I've seen the type of sleeve you're describing but maybe it's only required based on the foundation type? Ours is a monolithic slab instead of footings/stem walls so maybe that's why it wasn't in the plans for us or required per the county. Anyway, hope that helps and thanks for watching!

  • @averageliving4Life
    @averageliving4Life Před rokem

    Found your channel again. Starting this process in about 4 weeks! Really great videos, working through them all again, I'll ask a few questions at the end lol

  • @user-lr6uj7rs4k
    @user-lr6uj7rs4k Před 10 měsíci

    Thanks again for sharing all this - quick question, did you have to sleeve your plumbing pipes with a larger size pipe where the drain lines are passing through the footing? Or did you just wrap them with foam?

    • @BuildItLikeBeckhams
      @BuildItLikeBeckhams  Před 10 měsíci

      The plans didn't call for a sleeve so we just wrapped them with foam. Thanks for watching!