Critical Path Method (CPM)

Sdílet
Vložit
  • čas přidán 5. 09. 2024
  • UPDATE: We created a new CZcams channel. Please subscribe to / projectcontrolacademy to receive new training videos.
    For a complimentary series of video training in project controls please visit projectcontrol...
    This training video provides you an in-depth knowledge and understanding of the Critical Path Method (CPM). You will learn:
    - How the CPM method works
    - How the CPM method calculates the project finish date ( forward and backward pass calculations)
    - The concept of Total Float and Free Float and how to calculate them
    - Why floats are important in planning/ scheduling
    - What is the critical path
    check out: www.projectcont...

Komentáře • 176

  • @roninenlightened6350
    @roninenlightened6350 Před 6 lety +1

    Finally a CPM class on youtube with better English!

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety +1

    You are absolutely right J Ochoa. The examples state the logic right, but in the formulas there is a typo. The right formulas are: ES= Immediate Predecessors EF max and LF= Immediate Successors LS min. Thanks for catching the typos in the slides.

  • @RajeshKumar-dq6me
    @RajeshKumar-dq6me Před 8 lety +2

    Thanks . CPM has been explained in very simple way .Very easy to understand

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thanks Rajesh for your comment. Glad to hear that it was easy to understand :)

  • @flotfyr88
    @flotfyr88 Před 7 lety +3

    This was great! Before viewing this video, I didn't understand how the "longest duration" of the critical path determined the "minimum time for completion" of the project - but now I do. Great work!

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety +1

    You are right Ajyuk. The examples state the logic of ES & LS right, but in the formulas there is a typo. The right formulas are: ES= Immediate Predecessors EF max and LF= Immediate Successors LS min.

  • @hmoneymkr
    @hmoneymkr Před 10 lety +3

    Finally!!!! Someone who answered my question regarding which ES to use when more than one predecessor is present. I never knew which one and now I know to use the MAX. My professor seems to assume that his class knows
    this prior to starting his class. Frustrating. Keep up the good work Shohreh

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety +1

      Oh, I am so happy to hear that the video helped you understand the concept better. Thanks for watching the video and commenting on it. Keep up your great work in continuing your studies.

  • @bluecafe509
    @bluecafe509 Před 11 lety +3

    This is great, thank you! Covers everything I learned in class, except I can rewind and pause. :)

  • @deepanshupant7896
    @deepanshupant7896 Před 10 lety +3

    with videos like this we can challenge our prof that i can score full without attending your boring class. NICE VIDEO I LOVED IT .....

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      Thanks deepanshu pant for your comment. I am glad to hear that this video helped you better understand the Critical Path and float concepts.

  • @hendrikvanbrantegem7526
    @hendrikvanbrantegem7526 Před 9 lety +2

    thank you! it's so much easier when somebody explains it:) !

  • @cuserroro
    @cuserroro Před 7 lety

    I was searching for detailed example of free float. Thanks!

  • @MuthukumarRamasamyCloud
    @MuthukumarRamasamyCloud Před 10 lety +4

    I teach Proj Mgmt and this is one of the best presentation and the best in CPM out there over web. Good luck and hope to see more.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety +1

      Thanks Muthukumar for your uplifting comment. Much appreciated.

    • @longtran-hf9qj
      @longtran-hf9qj Před 10 lety

      Very good song .Could you please tell me the name of this song ?
      Thanks in advance.

  • @tarunrao23
    @tarunrao23 Před 10 lety +1

    Very Well Explained in 15 mins ..Our prof took more than 3 hours to explain the same

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      Thanks Tarun. Glad to hear that it was helpful for you :)

  • @crisbula11
    @crisbula11 Před 5 lety +1

    Very nice video but there are some mistakes. At min 3:01- ES is the highest of EF of all immediate predecessors. And at min 5:12 - LF = Immediate Successor's LS min

  • @mhlayel
    @mhlayel Před 10 lety +1

    Fantastic sequencing and overall presentation. You made it very easy to understand. Much appreciated effort.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety +1

      Many thanks for your comment. I am glad to hear that it was easy to understand :)

  • @christosmavrogiannis4331
    @christosmavrogiannis4331 Před 8 lety +2

    Awesome analysis, very appropriate voice for a speaker. Professional job, thank you.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Christos Thanks for your complement. Glad to hear that you liked the video on CPM.

  • @andrewpoverchuk8809
    @andrewpoverchuk8809 Před 9 lety +1

    I liked this video. It was concise with clear examples that precisely conveyed the concepts. A little boo-boo though at about 5:02: the narration does not match the content. Overall a very good job.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      +Andrew Poverchuk Thanks for your comment. We did make changes on the video to match the narration with the content at the point you mentioned. However, the new video is not uploaded here. Thanks for your attention to details.

  • @graceanthony
    @graceanthony Před 8 lety +2

    this is an excellent tutorial. I love the speaker and the graphics. Excellent, excellent. and one more time, excellent.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Grace Thanks for your excellent comment . You made my day an "excellent" one :)

  • @kaoakana
    @kaoakana Před 7 lety +1

    This was an excellent video - I'm in a PM course now and wish their videos were this good!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 7 lety

      Kao Akana thank you very much. I appreciate your positive feedback.

  • @johannwibowo6560
    @johannwibowo6560 Před 8 lety +1

    It's easy to understand. Good explanation, good examples. I recommend this to my colleagues.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thanks Johann for your comment and referring this video to your colleagues. Much appreciated.

  • @AndreBatesTrinidad
    @AndreBatesTrinidad Před 10 lety +1

    Very good showing of CPM. Thanks

  • @4EverBADFan
    @4EverBADFan Před 9 lety +1

    Wish I had come across this video two weeks ago! Finally something I can understand has helped me so much, thank you so very much, excellent presentation!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Oh, thanks Chris. It is awesome to hear that the video helped you understand the concept of the CPM method better. The video was my understanding and interpretation of the CPM method. I am glad to see that the concept is conveyed properly. Thanks again for your comment.

  • @Pepakudrna
    @Pepakudrna Před 9 lety +1

    So helpful :) ...you can really say that the textbook sucks, when video in different language than your own is better for comprehension :D

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Thanks Pepakudrna for your comment. I am happy to hear that the video helped you comprehend the text book better.

  • @hafizmuhammadasad6247
    @hafizmuhammadasad6247 Před 8 lety +1

    Plz clear my doubt.The correct formula to calculate early finish is:
    (a) EF=ES+duration
    (b)EF=ES+duration-1
    Which one is correct

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Hafiz, we have used (a) for simplicity of calculation and based on considering "start-of-the day" for calculating both start and finish dates. Computer scheduling programs use (b) ; the “start of the day” for calculating start dates and the “end of the day” for calculating finish dates. Using either (a) or (b) results in the same dates, if the assumption used for the calculation is clear. Great point you brought up here.

  • @muhammadraufaslam7976
    @muhammadraufaslam7976 Před 8 lety +1

    A really helpful tutorial, clearing all basic concepts

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thanks Muhammad for your comment. Happy to hear that it was helpful :)

  • @canyoneagle
    @canyoneagle Před 7 lety

    Good video. However, the forward pass example implies a SS relationship with the successor (using latest ES). Would be simpler to use latest EF of predecessors, since FS is the most common tie.

  • @efrosynimaher3454
    @efrosynimaher3454 Před 8 lety

    Great video. Thanks for the very good explanation. At backward pass Activity A, should the late finish be 5 because it is the minimum late start of activity B & C which is 10 & 5. Therefore the late start of Activity A is LS=LF-D in this case 5-2=3? This part confusing me because should this be zero like the activity D, I mean the late start is zero in activity D which is correct..

  • @franciscoFEUP
    @franciscoFEUP Před 9 lety

    It saved me ! Final exam this week

  • @harshavardhan3282
    @harshavardhan3282 Před 11 lety

    thanks for the video mam this very informative,especially total float and float are very easy to understand by your methodology

  • @McLuvin411
    @McLuvin411 Před 8 lety +1

    So much space for activities!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Morpheus Sam, I am not clear on your comment. I appreciate if you provide more information.

  • @TravelwithShama
    @TravelwithShama Před 10 lety +9

    nice mam better than my teachers

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Please be aware of a typo in the slides. The examples state the logic of ES & LS right, but in the formulas there is a typo. The right formulas are: ES= Immediate Predecessors EF max and LF= Immediate Successors LS min.

  • @nabutenati4853
    @nabutenati4853 Před 9 lety

    It helps more to visualize the terms

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Thanks Nabute. I tried to add the visuals according to my own undertanding of the Critical Path Method and float analysis.

  • @GirishNinjur
    @GirishNinjur Před 10 lety

    Good One, explained very clearly and in a simple manner, Thanks!!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      Thank Girish for your comment. Glad to hear that it helped you.

  • @marwayoussef2025
    @marwayoussef2025 Před 8 lety +1

    Amazing Explanation and analysis

  • @thadeu07
    @thadeu07 Před 8 lety +1

    Thanks for the detailed information of CPM
    It was easy for me to understand

  • @samabraham1457
    @samabraham1457 Před 8 lety +1

    *correction !!
    LF = immediate successors LSmin not LFmin

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Sam Abraham You are right. Thanks for your attention to details. The examples state the logic of ES & LS right, but in the formulas there is a typo. The right formulas are: ES= Immediate Predecessors EF max and LF= Immediate Successors LS min.

  • @Slavik822
    @Slavik822 Před 6 lety

    very easy & complicated explanation Thank you

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Thank you. I am glad to hear that you the vidoe helped you in your project. For more free Project Controls resources and trainings visit the ProjectControlAcademy website.

  • @Winky92000
    @Winky92000 Před 10 lety +1

    Thanks for the full explanation, really better than in school :)

  • @Nicktaylorhorrorshow
    @Nicktaylorhorrorshow Před 11 lety

    Wow - this is helping me stay sane this weekend!

  • @roxanrelano7937
    @roxanrelano7937 Před 11 lety

    thanks for the video it helps a lot especially in my assignment and coming final exam..

  • @ajyuk
    @ajyuk Před 11 lety

    Isn't the ES of an activity the maximum of the "Early Finish" of its preceding activities and Late Finish the minimum of the "Late Start" of its successors? Please rectify me if I am wrong.

  • @Songstress38208
    @Songstress38208 Před 11 lety

    Excellent video on CPM. Thank you!

  • @sharmilasheik
    @sharmilasheik Před 10 lety +1

    The best presentation. Thanks

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      Thanks Sheikh for your great comment :) It feels good to read the positive comments like yours.

  • @harishdhir2738
    @harishdhir2738 Před 9 lety +1

    Nice presentation Shohreh.......

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Thanks Don. I am glad to hear that you liked it. For more free Project Controls resources and trainings visit the ProjectControlAcademy website.

  • @s.andrabi8760
    @s.andrabi8760 Před 11 lety

    SG: Thanks for sharing the video. It is very useful to understand CPM and calculations. Very useful for the Project I am dealing with.
    Thanks one again..

  • @TusharManetheRaindrop
    @TusharManetheRaindrop Před 10 lety +1

    Thank you so much for this awesome representation.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      Thanks Tushar for your comment. I am glad to hear that you liked it :)

    • @TusharManetheRaindrop
      @TusharManetheRaindrop Před 10 lety +1

      You deserve this comment for this excellent presentation. Thanks once again

  • @indrarocks2012
    @indrarocks2012 Před 6 lety

    please help me understanding of project planning and scheduling..

  • @TheShirgo91
    @TheShirgo91 Před 9 lety +1

    thanks for video. its really clear video. very useful. But I need ur help. can u advise some books which can be useful for learning Project Mangament?

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      +Shirgylych Bayramov Thank you for your comment. I am glad to hear that you found the video helpful. If you help me better understand what exactly you are trying to learn in Project Management, I will be able to better help you.

    • @TheShirgo91
      @TheShirgo91 Před 9 lety

      +Shohreh Ghorbani I would like to learn all calculations which being used in Projects. for example Cost Performance index, Return on Investment etc..thats why I need a book in which I can find all these things.

  • @HalfHalfLife
    @HalfHalfLife Před 8 lety +1

    Thank you, you are a very effective teacher!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thank you very much. Glad to hear that it was helpful :)

  • @abbasjafri2473
    @abbasjafri2473 Před 9 lety +1

    Can you please explain how Start-A-B-E-Finish is 7 days?

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Abbas,
      You just add the duration of each activity to get the total path duration. The path Start-A-B-E-Finish is 7 days because by adding the duration of activities (0+2+1+4+0), you reach 7 days.

    • @abbasjafri2473
      @abbasjafri2473 Před 9 lety

      Thank you!

  • @mariasanz390
    @mariasanz390 Před 8 lety +1

    Very good! Thank you very much! It was really helpful

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Maria thank you for your comment. Glad to hear that your found the video helpful :)

  • @SlashMcBryt
    @SlashMcBryt Před 11 lety

    i try hard to understand because the process is short cutted can you please show all the calculations

  • @ahmedal-nabhani6726
    @ahmedal-nabhani6726 Před 9 lety +1

    شكرا جزيلا لك.
    That was really helpful & useful.

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Thanks Roxan. I am glad to hear that you found the video helpful. I am sure you will like my complenetary Project Controls trainings that I have recently posted. Get intant access to training video series that reveal secrets of Project Controls Industry and how to succeed in Project Controls & Project Management. Check it out at wwwProjectControlAcademycom

  • @arvindsinghrathore5243

    nicely explained... you should upload more videos...
    and thanx for this video :)

  • @tby7
    @tby7 Před 9 lety +1

    concise presentation...really helpful....Thank You!!

  • @amirbehzad2009
    @amirbehzad2009 Před 11 lety

    I think you are right, I had the same confusion

  • @temasek65
    @temasek65 Před 10 lety +1

    I was taught the formula for Free Float as " ES-EF-1" is this correct?

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      That's absolutely right Temasek. Actually this is the way that Primavera and other scheduling software calculate the Early and Finish dates. For simplicity and ease of understanding, I didn't include -1 or +1 in the video.

    • @temasek65
      @temasek65 Před 10 lety

      Thank you mdm.

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Great Ted. I am glad to hear that you found it helpful. Check out ProjectControlAcademy website for more resources.

  • @isratzaman8984
    @isratzaman8984 Před 8 lety +1

    Thank you for your tutorial. It was really effective!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Israt thank you for your comment. Much appreciated :)

  • @samirkaluskar2994
    @samirkaluskar2994 Před 9 lety +1

    That was very accurate and clear, the explanation also was to the point.. Thank you very much for this video :-)

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Samir Kaluskar Thanks for your comment. Much appreciated.

  • @chriscalawod9186
    @chriscalawod9186 Před 10 lety +2

    nice presentation! It helped me a lot!

  • @Avemeus
    @Avemeus Před 8 lety +1

    excellent presentation! Thank you very much!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Avemeus Thanks to you for leaving your positive comment here.

  • @whitemamba00
    @whitemamba00 Před 9 lety +1

    YOU ARE AMAZING, PERFECT ! finally I got it.

  • @dariatcyplukhina5130
    @dariatcyplukhina5130 Před 8 lety +1

    thank you for this video. such an awesome explanation!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thank you very much for your comment. It is awesome that you like the video.

  • @anirbanchakraborty9132
    @anirbanchakraborty9132 Před 8 lety +1

    A great tutorial. Thanks for your help!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      Thank you very much Anirban. Happy to hear that your found the tutorial helpful :)

  • @AsmaAsma-wz2sq
    @AsmaAsma-wz2sq Před 8 lety

    Thanks for uploading such an informative tutorial.... great explanation great work 👏👏

  • @chandunaidu4693
    @chandunaidu4693 Před 8 lety

    excellent teaching

  • @sunnynguyen8877
    @sunnynguyen8877 Před 9 lety +2

    so easy to understand! thank you

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      +Emily Khan Thank you for your comment. Glad to hear that it helped you better uderstand the concept of Critical Path.

  • @jochoa1140
    @jochoa1140 Před 11 lety

    I have dificulty with your logic. At the begining your example indicates that ES of any node is equal to the latest time of completion (EF) of all its predecesors (ES = Immediate Predecesors' EFmax). However, later you state that ES = Immediate Predecesors' ESmax. ES = Immediate Predecesors' EFmax, makes sense. ES = Immediate Predecesors' ESmax, does not make sense. Same argument in the Backward Pass. LF = Immediate Predecesors' LSmin, makes sense. LF = Immediate Predecesors' LFmin, does not.

  • @vadimkoller6232
    @vadimkoller6232 Před 9 lety

    Great video, very helpful and easy to understand :)

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Thanks Vadim for your comment. Glad to hear that the video was helpful for you.

  • @arpiyeghiazaryan5278
    @arpiyeghiazaryan5278 Před 5 lety

    thank you very much, the video was really helpful !!!

  • @Gy987654321
    @Gy987654321 Před 8 lety +1

    Very helpful. thank you!

  • @DonCorleoneMafiosi
    @DonCorleoneMafiosi Před 11 lety

    Excellent video, thank you so much for uploading.

  • @bamod78
    @bamod78 Před 8 lety

    Nice...very easy to understand

  • @lisheva1
    @lisheva1 Před 11 lety

    Thanks a lot very very clear explanation.

  • @shivashaw2220
    @shivashaw2220 Před 9 lety +1

    amazing video...great work

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Thanks Jhan. Check out more complementary deep-dive Project Controls training here at wwwProjectControlAcademy com

  • @nathangarret2009
    @nathangarret2009 Před 11 lety

    You are a genius

  • @AntaresCorScorpii
    @AntaresCorScorpii Před 9 lety

    Great video, very clear! Thank you!

  • @momzyadig
    @momzyadig Před 9 lety +5

    Can you replace my professor, please! Anyways, awesome content very easy to understand!

  • @adnanh2833
    @adnanh2833 Před 8 lety +2

    thank you, you are professional.

  • @NisankaMandara
    @NisankaMandara Před 10 lety +1

    a good explanation. Thanks a lot

  • @tkt228
    @tkt228 Před 9 lety

    Great video, really a life saver

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Thanks Tom. I am happy to hear that the video was helpful for you.

  • @ghorbanishohreh
    @ghorbanishohreh  Před 11 lety

    Many thanks everyone for your comments on the video. For more free Project Controls resources and trainings visit the ProjectControlAcademy website ( link to the website is under the video description).

  • @rajapradeep3556
    @rajapradeep3556 Před 9 lety +1

    Very good 1 n helped alot.
    A big thank you😋👌👍

  • @bhavani00772
    @bhavani00772 Před 7 lety

    Thank you very much very useful

  • @vikashkumar-qk8el
    @vikashkumar-qk8el Před 7 lety +1

    thank u

  • @nmindhe1
    @nmindhe1 Před 10 lety +1

    Thank you !!

  • @AaronMetallion
    @AaronMetallion Před 9 lety +3

    THANK YOU BESTAUBUVIUDEI EVER !!

    • @ghorbanishohreh
      @ghorbanishohreh  Před 9 lety

      Thanks Aaron. It is so kind of you. Glad to hear you like the video.

  • @jhzkhattak
    @jhzkhattak Před 12 lety

    very informative video. thx

  • @masoudtehrani1046
    @masoudtehrani1046 Před 9 lety +1

    Amazing!

  • @RealGame101
    @RealGame101 Před 8 lety +1

    good video. now i need to find a video that has lag times associated

    • @ghorbanishohreh
      @ghorbanishohreh  Před 8 lety

      +Ricky, may I ask what specific topic you are looking to explore? Are you looking for a video that describes how to run CPM calculations on activities that have lags? Is this what you are looking for?

    • @RealGame101
      @RealGame101 Před 8 lety

      +Shohreh Ghorbani I'm no longer looking for that information. that class is over lol

  • @konkataDineshkumar
    @konkataDineshkumar Před 9 lety +1

    thank you mam for this video

  • @anujgoyal2260
    @anujgoyal2260 Před 11 lety

    yeah , i think so.

  • @Anestori
    @Anestori Před 10 lety +1

    ty so much!

  • @conglekhanh2584
    @conglekhanh2584 Před 7 lety +1

    Exellent, thanks you

  • @tonycatman
    @tonycatman Před 10 lety

    3:02. "The early start of a node is the maximum early start of its predecessors".
    I think this is wrong. It should be the maximum early finish of its predecessors.

    • @ghorbanishohreh
      @ghorbanishohreh  Před 10 lety

      You are right Tony. The examples state the logic of ES & LS right, but in the formulas there is a typo. The right formulas are: ES= Immediate Predecessors EF max and LF= Immediate Successors LS min.