Push system vs Pull system in your value stream

Sdílet
Vložit
  • čas přidán 25. 06. 2024
  • The five principles of Lean look at Value, Value Stream, Flow, Pull, and Perfection.
    To apply Pull you must first have Flow, or have a product or service actually being delivered to your customer.
    Most organizations start in a Push system. Each person or step in their value stream or process works as hard as they can and as fast as they can to provide value to the next step.
    A Pull system instead works at the speed of the customer, ideally only producing a product or service when a customer demands it.
    DMAIC Decoded - Green Belt Masterclass on Problem Solving: www.udemy.com/course/dmaic-de...
    Connect with others new to Continuous Improvement: / lssnewbies
    Podcast: podcasters.spotify.com/pod/sh...
    Email: azim@beopportunity.com
  • Jak na to + styl

Komentáře • 13

  • @AbdulQadir-gf5nv
    @AbdulQadir-gf5nv Před 2 lety

    Wow … Excellent video with best simulation of real time situation 👍🏼👍🏼👍🏼

  • @AdnanMuazzam1
    @AdnanMuazzam1 Před 3 lety +2

    Great visual example 👍

  • @julianbaudler3309
    @julianbaudler3309 Před 2 lety

    Thank you! Now I finally understand what it's about!

  • @mmercer48
    @mmercer48 Před 3 lety +2

    This is a very good video. I'm going to use this with my team as a very good visual example of pull. Thank you for creating this.

  • @anupampal616
    @anupampal616 Před 2 lety

    Nicely explained....love from India

  • @AuSiuWai
    @AuSiuWai Před 2 lety

    it is the best visual example I have ever see.

    • @BeautifulOpportunities
      @BeautifulOpportunities  Před 2 lety

      Thank you, and it is very easy to do during a training. You just need 5 people and a rope!

  • @MegaZord23
    @MegaZord23 Před rokem +1

    Hi! Thanks for the video, i´m a little new in this. At 1:36, shouldnt the bootleneck be the step 2? it´s seems to be the slower process

    • @BeautifulOpportunities
      @BeautifulOpportunities  Před rokem +1

      That's a great call out. Certainly both step 2 and 3 at different points are the slowest steps and definitely where I've called out waste building up in the video would indicate step 2 being the bottleneck (at 1:36). If we improve step 3 we still must fix step 2 or no benefit will be seen.

    • @MegaZord23
      @MegaZord23 Před rokem +1

      @@BeautifulOpportunities Thank you for your reply ;) and keep the good work.

  • @imtiaze2k9
    @imtiaze2k9 Před 2 lety

    In PUSH system, inventory level is zero which is kind of ideal, isn't it?

    • @BeautifulOpportunities
      @BeautifulOpportunities  Před 2 lety +1

      It is unusual for an inventory level to be zero whether it is Push or Pull. The right level inventory has to be determined by the organization. Push systems are generally more likely to have a 'hidden factory' where scrap and other inventory builds up without a lot of oversight or acknowledgement.