Quantity surveying Interview questions - Variation

Sdílet
Vložit
  • čas přidán 21. 04. 2024
  • Are you preparing for a Quantity Surveyor interview focused on Variations? Here are some essential questions to help you ace the interview:
    These questions should provide a solid foundation for discussing your expertise in handling variations as a Quantity Surveyor. Good luck with your interview! 🚀 hashtag #QuantitySurveying hashtag #Variations hashtag #ConstructionManagement hashtag#interviewpreparation

Komentáře • 4

  • @waseemmanaf6623
    @waseemmanaf6623 Před 4 dny

    Hi Midhun, what you presented is correct if an adjustment to time for completion is not agreed under CL 13.3. If time for completion is not agreed or initiated by the contractor under CL 13.3 he can still claim the EOT under CL 20.1 identifying CL 8.4.(a) as the course of action.

  • @QSWORLD.
    @QSWORLD.  Před 2 měsíci

    Hi all , in variation process I had mentioned about clause 20.1 as notice , it is a mistake .. when explaining the eot confusion caused me to put that reference

  • @imrajahmedpunekar1194
    @imrajahmedpunekar1194 Před 2 měsíci

    Then what is the correct clause for Sending the notice...clause#20 is for contractors claims

    • @QSWORLD.
      @QSWORLD.  Před 2 měsíci

      Same clause if variation , send a notification of variation