Checking level of slab and beam bottom using AUTO LEVEL | Slab Checking

Sdílet
Vložit
  • čas přidán 5. 09. 2024
  • Hello friends,
    In this video I have explained full procedure of slab and beam bottom fixing and checking their levels using an auto levels directly on site. I have also shown it on drawing and all the calculations involved in checking levels If you liked it please subscribe to my channel and give a thumbs up on this video
    If you want more videos like this comment down below or you can connect with me on Instagram:
    Personal : @furqan.zari
    Official : @everything.civil
    Watch more videos like this :
    How Mahad Building collapsed?
    • How Mahad building col...
    Slab shuttering process shot on site
    • How slab shuttering an...
    3 Big Mistakes in Cantilever Beam
    • 3 Mistakes in Cantilev...
    Learn to read MEP sleeves Drawing
    • How to read MEP Sleeve...
    25 top selected practical civil engg questions
    • 25 Basic Practical Civ...
    Difference between stirrup and ties
    • Difference between sti...
    What is core cutting?
    • Is core cutting safe??...
    Column steel checking
    • CHECKING COLUMN REINFO...
    Design of two way slabs
    • DESIGN OF TWO WAY SLAB...
    #SlabLevel #AutoLevel #Surveying

Komentáře • 81

  • @hakemkhan3165
    @hakemkhan3165 Před 4 lety +1

    Wow..really informative with theoretical explanation

  • @sarthakmohapatra3738
    @sarthakmohapatra3738 Před 4 lety +1

    Exceptional video sir. U r a life saver. Thnx

  • @empoweracademy1322
    @empoweracademy1322 Před 3 lety +1

    Very nicely explained.....Keep up the good work.

  • @Avinashjadhav-qx2fr
    @Avinashjadhav-qx2fr Před 9 měsíci

    Best teaching technique sir... thank u so much😊

  • @lostworld1462
    @lostworld1462 Před 3 lety +2

    Really informative

  • @modassariqbal306
    @modassariqbal306 Před 4 lety +2

    Awesome videos sir 👌

  • @takeiteasesolutionchannel6956

    Tq bro nice explanation

  • @flywithzunera
    @flywithzunera Před 4 lety +1

    Bhai 10000000 likes ka option kash hota

  • @raffiehydermirza1803
    @raffiehydermirza1803 Před 3 lety

    The best video of levelling. Thanks a lot bhai. Make more videos and help us

    • @EverythingCivil
      @EverythingCivil  Před 3 lety +1

      Thanks..pls share.
      Yes will make on any topic u can recommend.

    • @raffiehydermirza1803
      @raffiehydermirza1803 Před 3 lety

      @@EverythingCivil make videos on leveling bhai like how to take excavation of footings through autolevel and how to transfer the levels etc; with drawings

  • @SiyakantChaudhary-xg9dl

    Good sir

  • @soumyaranjanpradhan6264
    @soumyaranjanpradhan6264 Před 4 lety +1

    Very informative video... carry on brother

  • @modassariqbal306
    @modassariqbal306 Před 4 lety +1

    Sir staff ko kaise read krte hai..us p v please 1 video banaye sir

  • @smileplease3600
    @smileplease3600 Před 4 lety +2

    Bro ek baar sankan area k baare bi bta dte....kynki sakan area k bich m kyi baar ek beam ata h to uska size nhi dia hota h....to uski side nikalne m thora confesse ho jate h....

  • @rahulchandravansi4557

    Sr bbs sikha dijiye jisase ekdam easy way me building ke sare drawing reading aur construction work bhi

  • @hdplanet7279
    @hdplanet7279 Před 2 lety

    Nice video

  • @DilshadKhan-601
    @DilshadKhan-601 Před rokem

    Very helpful video than you sir

  • @gaganpatidar9907
    @gaganpatidar9907 Před 4 lety +1

    very informative sir, can u share the size of shear walls, beams and columns with number of reinforcement. So we can idea about sizes of members for 20 storied building.

  • @minhajraja9809
    @minhajraja9809 Před 3 lety

    Best video clearly

  • @swapnilgaikwad7703
    @swapnilgaikwad7703 Před 2 lety

    Very very important video sir thank you

  • @princemohanty6936
    @princemohanty6936 Před rokem

    Thanku sir 🙏🙏

  • @MuhammadKamran-bx8ks
    @MuhammadKamran-bx8ks Před 3 lety +1

    Good👍

  • @alphamaverick4537
    @alphamaverick4537 Před rokem

    Informative⚡

  • @abdulkareem-kg8jn
    @abdulkareem-kg8jn Před rokem

    sir. very thanks

  • @pradippawar1709
    @pradippawar1709 Před 3 lety

    Very nice explained
    Sir plz explain the first level is to be taken while excavation by TBM

  • @saqibhussain5208
    @saqibhussain5208 Před 2 lety

    thank you sooo much very informative lecture.

  • @badalgallery
    @badalgallery Před 4 lety +1

    Nice

  • @bhagwatmane1668
    @bhagwatmane1668 Před rokem

    niceee broo

  • @badalgallery
    @badalgallery Před 4 lety +2

    What should be casting level of coloum..It's ok if column casting level is above the bottom of beam shuttering.

    • @EverythingCivil
      @EverythingCivil  Před 4 lety +1

      Yes it should be atleast 3-4 inches above beam bottom level.

    • @badalgallery
      @badalgallery Před 4 lety +1

      If column casting is above shuttering level of beam then cover under beam will increase in comparison of column buz bottom bar will rest on column ..Is it ok??

    • @EverythingCivil
      @EverythingCivil  Před 4 lety +2

      Yes. You are absolutely right.. we must make sure that beam bar is straight and column casting to be done such that required cover is available below the bottom bar.

    • @srisidhu5329
      @srisidhu5329 Před 3 lety

      @@EverythingCivil you should have done on slab leveling..

  • @raffiehydermirza1803
    @raffiehydermirza1803 Před 3 lety

    Make a video on excavation of footings too with auto level with a drawing shown as example

  • @msprojectplanning
    @msprojectplanning Před 11 měsíci

    Hero❤

  • @saitulaseeramm1047
    @saitulaseeramm1047 Před 3 lety +1

    Thank you sir... Well explained, keep posting like this

  • @letslearntv2692
    @letslearntv2692 Před 4 měsíci

    But how you put staff from 105 lvl in column when shuttering is already done to check level to take RL.

  • @t.sstatus0198
    @t.sstatus0198 Před rokem

    Sir auto level upper stidia se lower stidia ka distance kitna hoga?

  • @sunitashrestha9710
    @sunitashrestha9710 Před 3 lety +1

    Last is rl transfer then levelling

  • @ahmedfaiz1844
    @ahmedfaiz1844 Před 3 lety +1

    Sir, I have small doubt plz clear me, as you mention your first slab level is 103.7m and u have transferred temporary RL on a column that is 105.20, as u said we can transfer it through the tape simply by adding 1.5 mts from 103.7 slab level we get 105.20, my doubt is if we are working with auto level plz correct if my calculation is wrong, either I have to do, keeping staff on slab level we get some value let us example I am taking here 2.00m staff reading then the calculation must be (103.7+2.00=105.7) then we have to see 2.00mts from the staff and mark the point 105.7 as temporary RL right sir plz correct me or I have to assume directly 105.20 and then subtracting with 103.7 the value which we get should be marked by auto level plz correct me, and sir my one more doubt is as u got RL of the line of sight is 108.20mts on top of slab from your last temporary RL, and after marking this point anywhere on top of the slab, and as u said by subtracting from slab bottom level we get 1.05 and we have cross check through auto level but one of my SR.engineer first he use take height of instrument that is for example from your reference point (108.20 + staff reading) - slab bottom level) the value which he gets he use to cross-check and from that he used to correct slab level, sir plz don't mind I am a fresher civil engineer so that's the reason I have asked my doubt, plz clear my doubts, overall the information u shared is helpful, thank you.

  • @piyushraut2864
    @piyushraut2864 Před 2 lety

    Thank u so much sir

  • @nandkumarmestry2632
    @nandkumarmestry2632 Před 5 měsíci

    slab casting ek din me pura nahi ho to dusare din banate samay kya care lene chahiye

  • @sarthakmohapatra3738
    @sarthakmohapatra3738 Před 3 lety

    Super

  • @sibanandpradhan7535
    @sibanandpradhan7535 Před 3 lety

    Thanks

  • @KundanKumar-wx9gk
    @KundanKumar-wx9gk Před rokem

    Bhai aapne achche se Sam jhaye

  • @mohammadvahid1318
    @mohammadvahid1318 Před 2 lety

    Site p full detail m video bnao

  • @dennisngugi748
    @dennisngugi748 Před rokem

    Bring us the English version

  • @animeshadak3271
    @animeshadak3271 Před 3 lety +1

    COLOUMN ME JO RL FIX KIYA WO KAYSE KIYA?

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Project ka temporary benchmark ke hisab se hai..GL ko 100 RL lete hai.

  • @nileshsonawane324
    @nileshsonawane324 Před 3 lety

    Natural ground level ko 100rl liya hai kya sir...

  • @sonugupta7593
    @sonugupta7593 Před 3 lety

    Ya bhi bt do Beam ka bottom kitne per lagta hai yah kaise pata Karen plz reply dijiyega

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Apko kya janna hai detail me bataiye apko answer karta hu mai.

    • @sonugupta7593
      @sonugupta7593 Před 3 lety

      @@EverythingCivil building ki slab dalti hai Kuchh shuttering hoti hai na bheem ka bottom hota hai vah kaise decide hota hai kitni height per lagega Mujhe Janna hai Janna hai

    • @sonugupta7593
      @sonugupta7593 Před 3 lety

      @@EverythingCivil beam bottom kitne hight per lagega kaise pata Karen

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Pehle ap check karo ke apki floor to floor height kitni hai aur dekho ke beam depth kitni hai..samjho ke beam depth 500mm hai to apka beam bottom slab ke level se 500m down baithega column pe

    • @sonugupta7593
      @sonugupta7593 Před 3 lety

      @@EverythingCivil video Kyon Nahin banate sir

  • @vikash3200
    @vikash3200 Před 3 lety

    Shuttering ke bad column se S1 slab ka RL kase lenge

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Niche ke column pe level marking hogi waha se utahyege upar ke reinforce bar pe aur waha se baki slab ka level hoga

    • @vikash3200
      @vikash3200 Před 3 lety

      @@EverythingCivil shuttering ke pahle

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Find out height of slab bottom level from column marking then accordingly mark that level on reinforcement bar..

  • @amirahmadkhan1686
    @amirahmadkhan1686 Před rokem

    جناب فٹ کے حساب سے کرو

  • @shubhamkasat9688
    @shubhamkasat9688 Před 3 lety

    You depicted a wrong method.The level marking on column can't be taken from the slab level of 103.7 meter. You have to transfer TBM using auto level. TBM should be accurately defined. In your case, can you guarantee that the slab is accurately poured at 103.7 meter ? Answer is NO. Slab pour may be tight or slack from the actual 103.7 meter, which will only lead to uneven transfer of 105.2 meter on every column and eventually would lead to uneven level of upper slab and beam bottom shuttering. TBM may have to be shifted from the bottom floor. For that we have to calculate H.I.= R.L.(known) + Staff reading(from auto level). Then, your desired 105.2 m or any reading to be marked on column can be taken using auto level as you will already know staff reading needed to achieve TBM of 105.2 meter. H.I. - 105.2 = Staff reading (to be marked on column using staff and auto level). And you haven't even used auto level, simply measuring tape. Dude, please don't teach the wrong method, you may as well land engineer's into serious trouble.

    • @EverythingCivil
      @EverythingCivil  Před 3 lety

      Below ground for the first time level marking is done with the reference to the T.B.M and after that is done once level marking is done on upper columns by transferring it from the level marking of below column.