BBS of Footing | Bar Bending Schedule of House (Part- 2) | BBS कैसे निकालना है?
Vložit
- čas přidán 19. 09. 2020
- BBS कैसे निकालना है?
.
.
*Contact Details:-
Website:- www.cedkhomedesign.com/
Email ID:- civilengineer.deepakkumar18@gmail.com
Twitter: / erdeepak4kumar5
Facebook page: / er3deepak4kumar5
Instagram: / er.deepak4kumar5
*Join my Channel Membership
/ @civilengineerdeepakkumar
.
.
.
#BBS #BarBendingSchedule #FootingBBS
Aapke btane ka tarika best h sir jii
Thank you so much Bhiya...
Love you ...nice learning. ..Wonderful my brother.
Love you sir Itna behtarin Se Koi Nahin sir superb
Good night sir, bahat achha laga.
Well done. Keep it up
Good work sir ❤️❤️❤️
Bohut bhadiya sir ji
Bhout badya samajh aya sir
Very Nicely Explained...
Very very good sir ..
Very informative sir
Big fan sir love form kolkata
Very good lesson
Very good lesson ☺️☺️
Thank you so much 💗
Sir 10 mm bar used kar sakte ge na 125 mm spacing???
7:39 bahut bahut dhanywaad sir ji
Very good sir
Good Explanation. Thanks
Glad it was helpful!
Excellent video
Thank you very much!
Thankyou sir ❤❤❤
Very nice sir
Good subject.
Thank you sir
Oxm sir jiii 🙏
Sir aap nea calculation upto Ground level tak kiya hai ??
But sir lapping bar mea 1st floor, 2nd floor and upto roof (floor to floor distance -3.0m). Sir uska calculation kishe nekile ??
thankyou Sir
nice sir
tq sir
I request you please
fall selling ke bare me bhi bataiye.
Tq sir... Nxt video jaldi banao
Ok
Nice 👍
Thanks ✌
good
Waiting for next BBS of video..
Soon
can u explain why we provide Hook at the end of mesh of footing steel bar
Sir make more videos of BBS thank you
Interesting video..good job sir
Thank
👏👍👌
🙏👌
Smj ni aa rha rha thoda side ka bhi video/ photo dikhao ki kaha se kya h konsa hissa hai kya kya krte h fir aayega smj muje to
Sir rust remove keliye dr fixit rust remover use kar skate he kya .plz
Sir u didn't minus the clear cover in d1 and d2 which is 50mm
Sir bbs mujhe water taink ka sikhna hai
Number of mesh 2 kese aaya
Both side sariya lage gaa isliye 2 huwa
Sir ji stirrup ke calculation formula me +1khyoou. Let hai plz bataye...
Commercial Building ka Footing ka Bar bending Shedule V same issi tarika se hoga kya?
10mm@125 ?? Can we use for g+1?
Sir ji,ye method commercial Project pr Kam nhi krega kya
Beam ki depth kitni rahegi or usmai kitte mm ka bar aayega top/bottom mai kaise nikale
मेरी CL 1.252 आ रही है, आपने केसे निकाला 1.352
Number of mesh 2 kaise liya sir
Sir please make video on bbs of floor Beam of this series
Mujhe Bridge ka Niklna hai wo kese nikalega
Avrege silab ka bar ka bbs kaise nikale
Sir Which formula is 162
sir whre can i get this excel format
How to calculate when dimensions given in feet sir how it would be 4 feet in mm is 1200 how 🤔🤔 can u explain it sir
1 foot 30cm isne mm me le kya hai cm ko
Drawing kete padhenge mujhe uska tarika batado please sir
Sir...A Jo Apne L steel ka 150 mm liy wo kis basis PE liy..plz reply me sir
L ya to drawing me diya hota hai agar na diya ho to formula hota hai L=(2h/3)
Please upload bbs all vedio
Can I see all video?
Sir footing height kaise deduct krna h
Sir 2 inch subtract karna hai ki 4 inch ?
OK
भैया डबल जाल का BBS कैसे निकाले
L 150 kaise liya bhai vo batao
Footing me jo L turn karte hai uska 6"/150 mm hota hai.agar apke house diagram hai to usme hoga L ka size
Sir plzz jaldi daliye bbs of column and beam
Delhi Noida Haridwar me building ya house banwana ke liye contect kre 8273279127 contractor
sir ye 8 bar ka hai pura footing ka nhi h pura footing Mai 16 sariya lagega
Sir ji ap pora bar bending schedule karbaye
How to decide the spacing
Number of mash kese Aya sir
sir 1000 sq.feet single floor building me koun sa sariya kitna lagega ?
pls upload a detail review vidio on this topic
Delhi Noida Haridwar me building ya house banwana ke liye contect kre 8273279127 contractor
Pull ka kese nikale B.B.S
What is the cost of civil engineering
Sir slab kaa b bata dijye
Sir L me bottom se cover minus bhi Hota h
Nahi
@@VinodYadav-sc1ze why
1100+150+150 in this 150 how did you considered sir
L which is provided in the side of the mesh
2 floor building me 10 mm rod mesh me use kr sakte hain
Jo Jo bol rahe hai sir BBS ka ummid hai sara upload karenge🙏🙏
Ok
Jarur
BBS of column ka bhi daliye sir ..🙏
Ok
Coming soon
I am graduated civil engineering
Sir, clear cover 4 side se nai hoga kya??
Ha G savi side se hoga
Sir ji excel sheet share on description box
Sir cooling tower ka BBS nikalne ka video bna do please🙏
Where is word file sir ?
I have a doubt sir..
1400÷150= 9.3 ( not 7.3 ) please can check once..
1400 mm nahee bhai o 1100 mm hai...ok
Sir please screenshot lene k liye thoda space dijiye 🙏🙏
Plz share Excel sheet of footing BBS
Sir, what is the name of chapter and which subject BBS is part of
Please tell.
No any
Depth kaha hai
4:12 its wrong.. 8.3 ko hum 8 nehi lenge 9 lenge.. nehi to design unsafe hoga.. simple sa baat hai agar 8.3 ko aap 8 leloge toh us .3 reinforcement ka kaam kaun karega?? Isiliye hum usko 9 lenge safe keliye..
Dear sir 3p pile cap bbs AutoCAD pe please ❤️❤️
Coming soon
Sir clear cover 4 sides sye Nahi - karte
Mujhe bat karni hai
Hey dear engineer mama ji 😊
I am #mr_mk_singh . Do you know Mr. Hem Singh. he is my best friend. He sent me your channel link and I am here🙏
Love you mama ji ❤️❤️
Yes,
thanks
BBS colam ka bee banye sir
Coming soon
L 150 ayga ki kitna aayega vo kaisa pata chata hai
Excel mai formula use kr k bbs kaise solve kre sir
Bhai kuch update h to bhejo
2no.kya hai
ms excel ki file kha hai.?