  • It is important to know as a Planning Engineer how to create a Recovery Schedule, What you should / shouldn't do while creating a recovery schedule, and what are the tips and tricks of the recovery schedule.
    #Recovery_schedule #Planning_Tips # Ask_Hany
    ---------------
    Keep in Touch:
    Join our email Newsletter, we send useful free content regularly: planningengineer.net/newsletter/
    WhatsApp: +201277767728
    Email: Info@PlanningEngineer.Net
    Linked in: / planning-engineer-est
    FaceBook Page: / planningengineerdotnet
    FaceBook Group: / 1138400132963230
    Twitter: / planningeest
    Instagram: / planningengineerest
    ---------------

Komentáře • 24

  • @amnamunir9162
    @amnamunir9162 Před měsícem

    Asalam o alikum,sir there is any vedio regarding to recover /revised schedule in which you explain this steps practically? If do please share the link

  • @Aryanss5743
    @Aryanss5743 Před 2 lety +1

    Hi.Sir
    Please make a video on how to match planned value and earned value and Performance percent complete? Please make a video on this also.
    Thank You.

  • @mahadeermohamed6679
    @mahadeermohamed6679 Před 2 lety +1

    How did you find out the delay activities please make one video then update the progress schedule

  • @feroskhan9529
    @feroskhan9529 Před 2 lety +1

    Do we adjust "Out of Sequence" activities relationships before issuing?

  • @ShamithaNamasinghe
    @ShamithaNamasinghe Před rokem

    I tried this method but didnot get the output as wanted. Sir, can you do a video for this?

  • @aasimmohammad643
    @aasimmohammad643 Před 2 lety +3

    Hi . If i prepare a recovery schedule on a baseline does it mean i need to update all the completed and ongoing activities one by one ? Imaging a project with 10k activities and almost 6k activities finished . How will re update all the activities if i prepare a recovery on the baseline as you said.. I hope you can help me with an answer

    • @PlanningengineerNet
      @PlanningengineerNet  Před 2 lety +7

      Hello Engineer Aasim. Very simple, export the update from the updated schedule, import again to the new baseline recovery schedule and you are all done. I will try to make one video for that step by step

    • @PlanningengineerNet
      @PlanningengineerNet  Před 2 lety +3

      I made this video for you: czcams.com/video/gfic7eXu5bU/video.html

    • @kipshak7776
      @kipshak7776 Před rokem

      ​@@PlanningengineerNet

    • @khaledAhmed-eb4be
      @khaledAhmed-eb4be Před rokem

      Can you please make a video as case study on how to do it ,
      Adjusting actual dates and putting in baseline is not easy .
      as the activity might require 10 days but in real took 1 month due to stoppage in between and shifting to another area of activity but still showing 1 month ,and activity is not needed this much time delay but still show as one month .
      This is happened in so many activity same way , and rescheduling baseline again is not easy .

    • @khaledAhmed-eb4be
      @khaledAhmed-eb4be Před rokem

      Thanks alot eng.hany for your support , God bless you.

  • @syedabthahir4511
    @syedabthahir4511 Před 2 lety

    Hello sir
    Do have any experience in precast housing projects where morethan 1000 villas.

    • @PlanningengineerNet
      @PlanningengineerNet  Před 2 lety

      Yes i do :)

    • @syedabthahir4511
      @syedabthahir4511 Před 2 lety

      @@PlanningengineerNet
      Sir
      When i prepared schedule i divide the villas by zonewise. And mention start and finish date of each zones. But the client asking the schedule villa by villa as wells as floorwise.
      Can you please help me the following doubts.
      1.While preparing the detailed schedule should we show the erection only or other sub activities.such as screeding,Welding,grouting,inspection,finishing,sealant
      2.What will be best relationship between two zones/ two villas.
      3.While our scope is design,production,delivery & erection is it necessary to show production & delivery for all villas.
      4.When the BOQ showing price for elements types how we can input cost.
      5.do you have any standard daily progress reports template.
      Thanks in advance please help me to grow in my career .

  • @tanvirarif3719
    @tanvirarif3719 Před 2 lety

    Hello.....I did not understood, can you please show one with p6 example.

    • @PlanningengineerNet
      @PlanningengineerNet  Před 2 lety

      I will create a detailed video for that

    • @tanvirarif3719
      @tanvirarif3719 Před 2 lety

      @@PlanningengineerNet Thanks

    • @RiyadhScenes
      @RiyadhScenes Před 2 lety

      Yes I tried the way u said...but the planned percentage did not match with the performances percentage complete

  • @ahmadfikrisulaiman8698

    I like your accent sir. Which country you coming from?

  • @entrustvideos8871
    @entrustvideos8871 Před rokem

    This is theory. Practical would have been better

  • @Life_Vision
    @Life_Vision Před rokem

    Only talking