Water Tank Construction Process | Step by Step | Rebar Placement

Sdílet
Vložit
  • čas přidán 24. 06. 2021
  • #Construction #WaterTank #Animation
    Hi i am Mahadi Hasan from "CAD TUTORIAL BD". Today i will show an Animation About Water Tank Construction process. this video is very helpful for All who want to learn about Construction Work.
    Our Facebook Page - Cadtutorialb...
    So watch, shear, learn & subscribe for more update....
    / @cadtutorialbd
    (#Animation #Construction #Structural)

Komentáře • 69

  • @hydrogenperoxide9995
    @hydrogenperoxide9995 Před 2 lety +3

    This was really helpful. Subbed!

  • @ericwiltz6584
    @ericwiltz6584 Před 10 měsíci +6

    A very nice program!m though I didn't see any plumbing

  • @dipakpakrasi5995
    @dipakpakrasi5995 Před rokem +1

    A nice presentation

  • @ianconstruction
    @ianconstruction Před rokem +3

    Good educational video, I suggest it would be better if the corners are done the way we do corners for the Lift Shear Wall. Plus adding rebars at the corners.

  • @jonathanbadiang4478
    @jonathanbadiang4478 Před 6 měsíci +5

    few comments on this water tank structure,
    1. NO drain sump area.
    2. NO 150cm concrete exposure on the FGL.
    3. NO chamfer on all sides on the concrete.
    4. BITUMINOUS paint is required prior to backfilling.
    5. Waterproofing Or Epoxy Tank Linking must apply insides the tank.

  • @alirazawains512
    @alirazawains512 Před 2 lety +1

    this is really amazing man

  • @emmanueladeyeye4612
    @emmanueladeyeye4612 Před 2 lety +3

    As UK builder evry aspect o Australia concrete tank construction is sensible AN useful for clients and needs of the builders and users

  • @bpetnoi1472
    @bpetnoi1472 Před 8 měsíci +1

    I am presently designing such a tank in AutoCAD. If you take each unique piece of rebar and create them as blocks you can then insert blocks of each type. The benefit of this approach is you can then use the DX or data extraction command to count the blocks and make a BOM table of each type of bar and how many will be needed in the project.

  • @kashaftasribatalmiahbialriyad

    عمل رائع جداً

  • @smartsv4727
    @smartsv4727 Před rokem

    Super sir

  • @engferojnahian7094
    @engferojnahian7094 Před 2 lety +1

    ❣️

  • @jagboy69
    @jagboy69 Před 2 lety +4

    So how long have you worked for the steel industry?

  • @kashaftasribatalmiahbialriyad

    بالتوفيق ❤

  • @dipakpakrasi5995
    @dipakpakrasi5995 Před rokem +1

    👍👍👍👍👍

  • @jawanaram413
    @jawanaram413 Před rokem +8

    How you did slab without support under the slab

    • @sallysuay809
      @sallysuay809 Před 10 měsíci +2

      The bottom slab act as foundation and supported by soil. This is important to have check the actual bearing pressure and the soil pressure obtain from the tank;ie.dead load +live load and surcharge should not exceed actual bearing pressure of soil.

  • @onseriojr
    @onseriojr Před 7 měsíci +9

    Nice demo, but you left out many important parts.
    *Outlet pipes (cleaning and service) should have been fitted before pouring concrete to avoid cutting them when driving. That way, you avoid rust.
    *There is no overflow pipe provided. Should have installed before concrete.
    *There is no ventilation pipe installed
    *Therevis no provision for electrical if installing an ellectic pump.
    *The outside part of the wall should have added some tar or something to protect the wall from direct contact with the earth/soil/dirt
    *Manhole to tiny for a human being to get to clean, fix any cracks, or install aftermath fixtures.

  • @madhukarrai464
    @madhukarrai464 Před 2 lety +1

    Very good

  • @sumitmajhi4300
    @sumitmajhi4300 Před 10 měsíci +1

    Super 👌

  • @user-dk1re3ep5u
    @user-dk1re3ep5u Před rokem

    Isme plumbing work kaise hoga..
    Please uske liye bhi ek video share kijiye..

  • @muslimah97
    @muslimah97 Před 7 měsíci

    Dasyat..

  • @simonpunuhuru5096
    @simonpunuhuru5096 Před rokem +3

    can you show how to calculate for the bottom bar slab and side wall bars?

  • @Abdullah-kl9be
    @Abdullah-kl9be Před rokem +1

    Nice video! which program did you use to make this animation?

  • @africanabdusalaam1943
    @africanabdusalaam1943 Před rokem +1

    What's the length, width and The depth of the tank

  • @abdulrahimkhan5714
    @abdulrahimkhan5714 Před 2 lety +1

    Agra District R.C.C. Water Tank normal thickness all Side walls of Readymade 2000 Liter. Capacity water Tank in Complete Pieces is seen selling to Peoples Constructing their House.

  • @TalukdarAhmed-uo8bo
    @TalukdarAhmed-uo8bo Před 7 měsíci

    Good

  • @ezeeposse1
    @ezeeposse1 Před rokem +2

    Trying to understand the need for the upper corner rebars purpose. Could someone explain to me please?

    • @mrb4563
      @mrb4563 Před rokem +1

      Me too need an explanation for that

    • @dee900
      @dee900 Před rokem +1

      This is just an educated guess but I think they are stiffeners that provide additional strength and stability by resisting lateral loads

  • @patitpabandas1806
    @patitpabandas1806 Před 2 měsíci

    What will be the cost of 1lakh lit under ground water tank of rcc.?

  • @keerthanalokesh2883
    @keerthanalokesh2883 Před 2 lety

    Heyy Keerthana

  • @shamimmolla5528
    @shamimmolla5528 Před 3 lety

    থ্যাঙ্ক ইউ

  • @qamarbaloch1
    @qamarbaloch1 Před měsícem

    3500 liters underground water tank ki labour kitni honi chahyey

  • @mustakkhan4844
    @mustakkhan4844 Před rokem +2

    Where is water stopper ? You didn't provide it

  • @zi953
    @zi953 Před 4 měsíci +1

    extension name for rebar ?

  • @RomeoDiomangay
    @RomeoDiomangay Před 17 dny

    Paano po ang porma Niya

  • @SamsulRahaman408
    @SamsulRahaman408 Před 2 lety

    kivabe apply korbo sir bolen

  • @infracontservices8784

    i need sketup designeer this type desine

  • @rahilrizvi4404
    @rahilrizvi4404 Před rokem +2

    Sir which software u use for make this video?

    • @cadtutorialbd
      @cadtutorialbd  Před rokem +1

      Thanks for your Comments. I used SketchUP software for this video.

  • @pingpingchan4197
    @pingpingchan4197 Před rokem

    深坑

  • @Amblog555
    @Amblog555 Před rokem

    no sleeves?????

  • @anilpalve5569
    @anilpalve5569 Před rokem

    Please tellcosting

  • @muthuvinodhkumar7645
    @muthuvinodhkumar7645 Před 2 lety

    Cc layer mean

  • @thestonestructure7508
    @thestonestructure7508 Před 2 lety +1

    Where's Water line?

  • @davidbruce5377
    @davidbruce5377 Před 7 měsíci

    Where is the bentonite strip?

  • @shishielsingh4168
    @shishielsingh4168 Před rokem +1

    Itne bars main to Ghar-bar bhik jayega 😅😅

  • @shamimmolla5528
    @shamimmolla5528 Před 3 lety

    স্যার আমি কি আপনার মোবাইল নাম্বারটা পেতে পারি

  • @subratali2325
    @subratali2325 Před 7 měsíci

    Ek ek bareek bar zoom karke batao kya kya hai aur kaise lagate hao

  • @joesantos3717
    @joesantos3717 Před 10 měsíci

    Unless that's a giant water tank or you want to store nuclear waste its a little over engineered...

  • @felisbertolopes43
    @felisbertolopes43 Před 2 lety

    Have BoQ

  • @Kiwi_As
    @Kiwi_As Před 2 lety +1

    I clicked on this thinking it was a Minecraft build lol

  • @rakhmadwibisono1871
    @rakhmadwibisono1871 Před rokem +1

    Where is the water stop..?

  • @kdwalker3389
    @kdwalker3389 Před 2 měsíci

    You say step by step, but I didn't see any wall forms steps, water stops or bracing, sump pump area etc. This is a joke right?

  • @user-mx7rw4nc4j
    @user-mx7rw4nc4j Před měsícem

    can you send me this via pdf if possible

  • @pkjena1173
    @pkjena1173 Před 2 lety

    I need some help.
    Can I contact you??

  • @qamarbaloch1
    @qamarbaloch1 Před měsícem

    3500 liters underground water tank ki labour kitni honi chahyey