MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork

Sdílet
Vložit
  • čas přidán 30. 11. 2023
  • MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork
    About This Video Content,
    In this video Er. Narendra Patle explained about, we talk about 7 days slab cycle with mivan shuttering, will discuss procedure with the activities to follow on site each day to achieve 7 days cycle
    This video covers all these topics
    ▶️Day 1
    - Grid line work
    - Thesi work (fixing of wooden planks )
    - Complete vertical column, shear wall and nonstructural wall reinforcement work
    ▶️Day 2 and 3
    - Erection of wall panels, deck panels with all chajjas elevation work
    ▶️Day 4
    - Complete Beam and slab reinforcement work with covering
    ▶️Day 5
    - Complete all Electrical Conduting work and MEP sleeves and cutouts if needed
    ▶️Day 6
    - Complete Gridline checking and supporting work of slab
    ▶️Day 7
    - Complete checking work of RCC, architect, quality and MEP work as per approved drawing and with respecting departments
    - Final do Concrete Casting work of slab
    and many more...
    ===================================================================
    Download all Courses free ( BBS Excel Sheet / Drawing / Useful pdf )
    (Note: Videos and documents will get update daily, so stay tuned for more information )
    docs.google.com/spreadsheets/...
    Download file in pdf
    docs.google.com/spreadsheets/...
    Please Subscribe: / civilconstruct
    ===================================================================
    Visit our Channel for Civil Engineering Knowledge:
    / dndconstruction
    Visit our Channel for lifestyle & Fitness
    / @dineshlifestyle
    Follow us on INSTAGRAM: civil_const...
    Join us on Telegram: t.me/civil_construct
    Follow us on FACEBOOK: / 102249415176766
    ===================================================================
    #mivanshuttering #7daysslabcycle #dndconstruction
    mivan technology construction
    Slab cycle in construction
    complete procedure to follow to complete slab in 7 days by mivan technology
    ===================================================================
    Disclaimer - This video is for educational purpose only. Copyright
    Disclaimer Under Section 107 of the Copyright Act 1976, allowance is
    made for "fair use" for purposes such as criticism, comment, news
    reporting, teaching, scholarship, and research. Fair use is a use
    permitted by copyright statute that might otherwise be infringing.
    Non-profit, educational or personal use tips the balance in favor of
    fair use .
  • Věda a technologie

Komentáře •